Soldier Study Guide · MOS study guides
Study MOS 12N (Horizontal Construction Engineer) with plain-language flashcards for your Army job, board prep, and related tasks. Check current Army publications for the latest updates.
Looking for a different job? Browse all Army MOS flashcards.
Study modules
12N – Deep Dive: Duties, Equipment Operations, Safety & Standards
Source: DA Pam 611-21 ch. 10C (10-12N, Oct 2026 copy); TM 3-34.62 (Earthmoving Operations, 30 May 2025 incl. C1, 29 Jul 2026); TM 3-34.43 (3 Apr 2015); TM 3-34.64 (25 Sep 2012); TM 3-34.55 (3 Aug 2012); TM 3-34.42 (Dec 2012); ATP 3-34.40 (14 Apr 2023); FM 3-34 (16 Dec 2025). Complements mos-12n; does not repeat those cards. Verify current editions.
- 12N deep dive: Is 12N an Army Civilian Acquired Skills Program (ACASP) designated MOS?
- Yes. MOS 12N is an ACASP designated MOS.
- DA Pam 611-21 (ch. 10C, Oct 2026 copy), 10-12N heading
- 12N deep dive: How do 12N duties progress from intern to senior level?
- Duties start with operating heavy equipment at an intern level and progress to senior equipment operator level with supervisory responsibilities for personnel, construction projects, obstacle emplacement, and counter-obstacle operations involving construction equipment.
- DA Pam 611-21 (ch. 10C, Oct 2026 copy), 10-12N a
- 12N deep dive: Besides basic equipment operation, what basic skills does a 12N1O learn?
- Interpreting basic grade stakes and identifying basic soil properties.
- DA Pam 611-21 (ch. 10C, Oct 2026 copy), 10-12N a(1)
- 12N deep dive: What basic crawler-tractor tasks does a 12N1O perform?
- Clearing, grubbing, stripping, excavating, backfilling, constructing ditches, stockpiling, and push-loading scrapers.
- DA Pam 611-21 (ch. 10C, Oct 2026 copy), 10-12N a(1)
- 12N deep dive: What basic motorized-scraper tasks does a 12N1O perform?
- Excavating and spreading fill material.
- DA Pam 611-21 (ch. 10C, Oct 2026 copy), 10-12N a(1)
- 12N deep dive: What basic scoop-loader tasks does a 12N1O perform?
- Stockpiling, backfilling, and loading haul units.
- DA Pam 611-21 (ch. 10C, Oct 2026 copy), 10-12N a(1)
- 12N deep dive: What basic motorized-grader tasks does a 12N1O perform?
- Scarifying, spreading, leveling, and constructing V ditches.
- DA Pam 611-21 (ch. 10C, Oct 2026 copy), 10-12N a(1)
- 12N deep dive: What basic hydraulic-excavator tasks does a 12N1O perform?
- Excavating, stockpiling, backfilling, constructing ditches, and loading haul units.
- DA Pam 611-21 (ch. 10C, Oct 2026 copy), 10-12N a(1)
- 12N deep dive: What basic backhoe-loader tasks does a 12N1O perform?
- Excavating, stockpiling, backfilling, constructing ditches, and loading haul units.
- DA Pam 611-21 (ch. 10C, Oct 2026 copy), 10-12N a(1)
- 12N deep dive: What basic dump-truck tasks does a 12N1O perform?
- Driving, spreading, and dumping material.
- DA Pam 611-21 (ch. 10C, Oct 2026 copy), 10-12N a(1)
- 12N deep dive: What basic water-distributor tasks does a 12N1O perform?
- Driving, loading, and spraying water.
- DA Pam 611-21 (ch. 10C, Oct 2026 copy), 10-12N a(1)
- 12N deep dive: What basic roller tasks does a 12N1O perform?
- Compacting material with a sheep’s-foot roller, a smooth-drum roller, and a vibratory roller.
- DA Pam 611-21 (ch. 10C, Oct 2026 copy), 10-12N a(1)
- 12N deep dive: What basic tractor-trailer task does a 12N1O perform?
- Transporting heavy construction equipment.
- DA Pam 611-21 (ch. 10C, Oct 2026 copy), 10-12N a(1)
- 12N deep dive: Besides limited supervision, what does a 12N2O provide on horizontal construction projects?
- 12N2Os are senior and become primary operators for all finishing work and complex operating situations. They provide guidance to less experienced equipment operators on operating techniques, procedures, and operator maintenance.
- DA Pam 611-21 (ch. 10C, Oct 2026 copy), 10-12N a(2)
- 12N deep dive: What are the major duties of a 12N3O?
- Serve as a Horizontal Construction Supervisor or Section Sergeant. Supervise the use of heavy construction and lifting equipment on construction projects; calculate equipment and operator requirements to help develop construction project estimates; and organize and direct mobility and countermobility missions.
- DA Pam 611-21 (ch. 10C, Oct 2026 copy), 10-12N a(3)
- 12N deep dive: What are the major duties of a 12N4O?
- Serve as a Senior Horizontal Construction Supervisor or Platoon Sergeant. Organize the overall construction workload; use project-management techniques to develop and execute construction projects and coordinate supporting units; plan, organize, and supervise all engineer construction equipment operations, including mobility and countermobility missions; and develop and execute a quality-control plan and standard operating procedures.
- DA Pam 611-21 (ch. 10C, Oct 2026 copy), 10-12N a(4)
- 12N deep dive: What minimum OPAT scores does DA Pam 611-21 list for 12N?
- Standing Long Jump 120 cm, Seated Power Throw 350 cm, Strength Deadlift 120 lbs, and Interval Aerobic Run 36 shuttles, in Physical Demand Category “Moderate” (Gold).
- DA Pam 611-21 (ch. 10C, Oct 2026 copy), 10-12N b(4)(b)
- 12N deep dive: What driver’s-license rule applies to 12N applicants?
- They must have a valid motor vehicle license from any of the 50 states or U.S. territories (photo ID or paper form, in accordance with the issuing state’s or territory’s laws) in order to ship from the entry station to BCT or AIT.
- DA Pam 611-21 (ch. 10C, Oct 2026 copy), 10-12N b(5)
- 12N deep dive: What vision requirement does DA Pam 611-21 list for 12N?
- Red/green color discrimination.
- DA Pam 611-21 (ch. 10C, Oct 2026 copy), 10-12N b(3)
- 12N deep dive: How much civilian experience is required to qualify for 12N under ACASP?
- Two years of experience operating each of the following: crawler tractor, grader, loader, hydraulic excavator, backhoe loader, rollers, tractor trailers, and dump trucks.
- DA Pam 611-21 (ch. 10C, Oct 2026 copy), 10-12N b(7)
- 12N deep dive: Does an Initial Entry Trainee who qualifies for 12N under ACASP have to attend AIT?
- No. Per table 9-1 of the pamphlet, an IET who qualifies under ACASP is not required to attend AIT. After Basic Combat Training, the Soldier is processed in accordance with initial assignment instructions.
- DA Pam 611-21 (ch. 10C, Oct 2026 copy), 10-12N b(7)(a)
- 12N deep dive: Who approves and validates ACASP qualification for a 12N IET?
- The U.S. Army Engineer School (USAES), Engineer Personnel Development Office (EPDO).
- DA Pam 611-21 (ch. 10C, Oct 2026 copy), 10-12N b(7)(b)
- 12N deep dive: What additional skill identifiers does DA Pam 611-21 list for 12N?
- B9 – Bradley Fighting Vehicle (personnel only); C3 – Well Drilling; C4 – Crane Operator (skill level 1–2 only); M9 – Master Driver Trainer (skill level 3–4, effective 202610); P6 – Project Management (skill level 2 through 6, personnel only); Q6 – Protection Cell Operations (skill level 4 through 6, personnel only); R7 – Army Reconnaissance (skill level 3 and above, personnel only); S4 – Sapper Leader (SPC (P), SGT, and SFC personnel only; E6 positions and personnel); and Y2 – Transition (personnel only).
- DA Pam 611-21 (ch. 10C, Oct 2026 copy), 10-12N c(1) through c(9)
- 12N deep dive: At what skill levels may a 12N hold ASI C4 (Crane Operator)?
- Skill levels 1 and 2 only.
- DA Pam 611-21 (ch. 10C, Oct 2026 copy), 10-12N c(3)
- 12N deep dive: What skill levels may hold ASI P6 (Project Management) on 12N?
- Skill levels 2 through 6, for personnel only.
- DA Pam 611-21 (ch. 10C, Oct 2026 copy), 10-12N c(5)
- 12N deep dive: What basic management phases must project managers follow, according to TM 3-34.62?
- Planning, organizing, staffing, directing, controlling, and executing. Managers must also meet project-directive deadlines and conform to safety and environmental protection standards.
- TM 3-34.62 (30 May 2025 incl. C1, 29 Jul 2026), para 1-1
- 12N deep dive: What should a manager consider when selecting earthmoving equipment for a task?
- The operational capabilities of the machine and equipment availability, then visualize the best use of available equipment based on soil considerations, zone of operation, and project-specific requirements.
- TM 3-34.62 (30 May 2025 incl. C1, 29 Jul 2026), para 1-2
- 12N deep dive: How is production rate calculated?
- Production rate equals the unit of work done divided by the unit of time, such as cubic yards per hour, tons per shift, or feet of ditch per hour.
- TM 3-34.62 (30 May 2025 incl. C1, 29 Jul 2026), para 1-4
- 12N deep dive: How is “time required” related to the production-rate formula?
- It is the inverse of the production-rate formula and is used in project scheduling to calculate the time needed to complete a specific amount of work, expressed in units such as hours per 1,000 cubic yards, hours per acre, days per acre, or minutes per foot of ditch.
- TM 3-34.62 (30 May 2025 incl. C1, 29 Jul 2026), para 1-5
- 12N deep dive: In what three volume states can earthmoving material be measured?
- Bank cubic yard (BCY)—one cubic yard in its natural or undisturbed state; loose cubic yard (LCY)—one cubic yard after it has been disturbed by excavation; and compacted cubic yard (CCY)—one cubic yard after compaction.
- TM 3-34.62 (30 May 2025 incl. C1, 29 Jul 2026), para 1-6
- 12N deep dive: Into what three categories are earthmoving materials typically placed?
- Rock, soil (common earth), and unclassified (a combination of rock and soil). Rock cannot be removed by ordinary earthmoving equipment and requires drilling and blasting. Soil removal does not require explosives, though ripping may be needed to loosen consolidated deposits.
- TM 3-34.62 (30 May 2025 incl. C1, 29 Jul 2026), para 1-7
- 12N deep dive: What material properties must be analyzed and built into an earthmoving plan?
- Loadability, moisture content, percentage of swell, and compactability.
- TM 3-34.62 (30 May 2025 incl. C1, 29 Jul 2026), para 1-8
- 12N deep dive: What is loadability?
- A general material property: if a material is easy to dig and load, it has high loadability; if it is difficult to dig and load, it has low loadability. Certain clays and loams are easy to excavate or load into a scraper in their natural state.
- TM 3-34.62 (30 May 2025 incl. C1, 29 Jul 2026), para 1-9
- 12N deep dive: Why does moisture content matter in earthmoving?
- It affects the unit weight and handling properties of the soil. All soil naturally contains some moisture, and the amount retained depends on weather, drainage, and the soil’s retention properties. Mechanical or chemical treatment can alter moisture content.
- TM 3-34.62 (30 May 2025 incl. C1, 29 Jul 2026), para 1-10
- 12N deep dive: What is swell, and how much does dry clay typically swell when excavated?
- Swell is the percentage of expansion that occurs when earth or rock is excavated and voids are created. Dry clay typically swells by 40 percent, so 1 cubic yard in place expands to 1.4 cubic yards when excavated.
- TM 3-34.62 (30 May 2025 incl. C1, 29 Jul 2026), para 1-11
- 12N deep dive: Why is soil usually compacted to a higher density than its natural state?
- Because higher density is linked to increased strength, reduced settlement, improved bearing capacity, and lower permeability. The required density is specified in the project guidelines.
- TM 3-34.62 (30 May 2025 incl. C1, 29 Jul 2026), para 1-12
- 12N deep dive: How can soil weight cause a scraper to hit its volume limit or its weight limit first?
- If the material is relatively light, such as cinder, a scraper may fill its volumetric capacity (for example, 25 cubic yards) before reaching its rated load capacity (for example, 50,000 pounds). If the load is heavy gravel, which may weigh more than 3,000 pounds per cubic yard, it may exceed the gravimetric capacity before the bowl is full.
- TM 3-34.62 (30 May 2025 incl. C1, 29 Jul 2026), para 1-13
- 12N deep dive: Which volume unit is typically the standard of comparison in earthmoving?
- Bank cubic yards (BCY). The same amount of material occupies different volumes as BCY, LCY, and CCY, so BCY is typically used for comparison.
- TM 3-34.62 (30 May 2025 incl. C1, 29 Jul 2026), para 1-13
- 12N deep dive: How do you convert loose cubic yards to bank cubic yards?
- Multiply LCY by the load factor from table 1-2 (LCY × load factor = BCY). Similar factors are used to convert to a compacted state, depending on the degree of compaction.
- TM 3-34.62 (30 May 2025 incl. C1, 29 Jul 2026), para 1-14 and table 1-2
- 12N deep dive: What is the load factor for dry clay, and what does that mean for a 25-LCY scraper load?
- The load factor for dry clay is 0.72. A scraper carrying 25 LCY of dry clay is carrying 18 BCY (25 × 0.72).
- TM 3-34.62 (30 May 2025 incl. C1, 29 Jul 2026), para 1-15
- 12N deep dive: What three zones of operation should be considered when selecting earthmoving equipment?
- The power zone, the slow-speed hauling zone, and the high-speed hauling zone. A mass diagram helps show how materials should be moved and helps identify these zones (see also TM 3-34.48-1).
- TM 3-34.62 (30 May 2025 incl. C1, 29 Jul 2026), para 1-16
- 12N deep dive: What conditions define the power zone, and what equipment does it require?
- Conditions that need maximum power, such as rough terrain, steep slopes, pioneering operations, or extremely heavy loads. Work in these areas requires crawler tractors that can generate high drawbar pull at slow speeds; more traction helps the tractor reach its full potential.
- TM 3-34.62 (30 May 2025 incl. C1, 29 Jul 2026), para 1-17
- 12N deep dive: What defines the slow-speed hauling zone?
- Power, rather than speed, is still the crucial factor, but site conditions are slightly better than in the power zone and the haul distance is short. Ground conditions do not allow fast travel, dozing is not economical at the required distance, and the haul is not long enough for scrapers to travel at high speeds, so dozers and scrapers achieve the same speed.
- TM 3-34.62 (30 May 2025 incl. C1, 29 Jul 2026), para 1-18
- 12N deep dive: What defines the high-speed hauling zone?
- Good ground conditions or long, well-maintained haul roads; haul distances long enough to reach maximum travel speeds; and push tractors (pushers) available to assist in loading. Production increases when the scraper works at its maximum speed, so this condition should be reached as soon as possible.
- TM 3-34.62 (30 May 2025 incl. C1, 29 Jul 2026), para 1-19
- 12N deep dive: What speed caution does TM 3-34.62 give for hauling operations?
- Operate equipment at safe speeds to prevent personal injury or premature failure of the machine’s major components, and conduct hauling operations safely and efficiently.
- TM 3-34.62 (30 May 2025 incl. C1, 29 Jul 2026), para 1-19 caution
- 12N deep dive: How does TM 3-34.62 describe a dozer, and what is it standard equipment for?
- A dozer is a tracklaying crawler or a wheel tractor equipped with a blade. It is designed to provide high drawbar pull and traction effort and is standard equipment for land clearing, dozing, and assisting in scraper loading. It can also be equipped with a rear-mounted winch or rippers.
- TM 3-34.62 (30 May 2025 incl. C1, 29 Jul 2026), ch. 2 introduction (immediately before para 2-1)
- 12N deep dive: Why should dozers be transported on heavy trailers between or within projects?
- To avoid excessive track wear and to prolong the operational life of the machine. Crawler tractors also exert low ground-bearing pressure, which adds to their versatility.
- TM 3-34.62 (30 May 2025 incl. C1, 29 Jul 2026), ch. 2 introduction (immediately before para 2-1)
- 12N deep dive: How are military dozers classified, and what are examples of each class?
- They are classified by weight and pounds of drawbar pull. The DEUCE is a light-class dozer. The medium crawler tractor (MCT) and the D7 are examples of a medium-class dozer.
- TM 3-34.62 (30 May 2025 incl. C1, 29 Jul 2026), para 2-1 and figures 2-1 and 2-2
- 12N deep dive: What is a dozer blade made of, and how can it be adjusted?
- A moldboard with replaceable hardened-steel cutting edges and side bits, connected by push arms and tilt cylinders or a C-frame. The blade may be tilted (one edge raised or lowered), pitched (top tilted forward or back to change the cutting-edge angle), or, if mounted on a C-frame, angled from the direction of travel. A single mount may incorporate any two of these features.
- TM 3-34.62 (30 May 2025 incl. C1, 29 Jul 2026), para 2-2
- 12N deep dive: How is a straight dozer blade mounted, and how far can it be tilted or pitched?
- It is mounted in a fixed position, perpendicular to the line of travel. It can be tilted and pitched forward or backward within a 10° arc. Tilting concentrates driving power on a limited length of the blade; pitching increases penetration for cutting or reduces it for back dragging.
- TM 3-34.62 (30 May 2025 incl. C1, 29 Jul 2026), para 2-3
- 12N deep dive: When is an angle blade most effective, and how far can it be angled?
- For side-casting when backfilling or making sidehill cuts, and also for rough grading, spreading piles, or windrowing. Angle blades are 1 to 2 feet wider than straight blades and can be angled up to 25° left or right of perpendicular, or used as a straight blade. When angled, the blade can be tilted but cannot be pitched.
- TM 3-34.62 (30 May 2025 incl. C1, 29 Jul 2026), para 2-4
- 12N deep dive: What is a Rome K/G blade used for, and how should a large tree be cut with it?
- It is a special-purpose clearing blade, fixed at a permanent angle with a stinger, used to cut brush and trees at or a few inches above ground level rather than uprooting them. For a large-diameter tree, use the stinger to split and weaken the tree first, then cut it off and push it over with the blade. Keep the stinger and cutting edge sharp.
- TM 3-34.62 (30 May 2025 incl. C1, 29 Jul 2026), para 2-5 and figure 2-3
- 12N deep dive: What should be done before starting dozer clearing, and how should debris be handled?
- Address environmental-protection considerations first. Plan the work so debris is disposed of in one handling, and try to travel in one direction to avoid damaging trees. Vegetation may be sheared at ground level, or stumps and roots may have to be removed, depending on the project specifications.
- TM 3-34.62 (30 May 2025 incl. C1, 29 Jul 2026), para 2-6
- 12N deep dive: According to table 2-1, about how many hours per acre does a medium tractor need for normal area clearing?
- 2.5 hours per acre for light cover (trees 12 inches or less), 5.0 hours for medium cover (12 to 18 inches), and 10.0 hours for heavy cover (18 inches), based on maximum tree size. For strip-type clearing, increase the table 2-1 values by 60 percent.
- TM 3-34.62 (30 May 2025 incl. C1, 29 Jul 2026), para 2-6 and table 2-1
- 12N deep dive: How should a dozer remove small trees and brush, and about how much can a medium tractor clear per hour?
- Operate with the blade slightly below ground level so the blade cuts, breaks off, or uproots most of the tree and bends the rest for easier removal on the return trip. A medium tractor with a dozer blade can clear and pile about 0.25 acres of brush or small trees per hour.
- TM 3-34.62 (30 May 2025 incl. C1, 29 Jul 2026), para 2-7
- 12N deep dive: How should a dozer remove a medium-sized tree (7 to 12 inches in diameter)?
- Raise the blade as high as possible for leverage, push the tree over slowly, then quickly back up to avoid the rising roots. Lower the blade and drive forward to lift out the roots. On average, a medium tractor takes 2 to 9 minutes to clear and pile a medium tree.
- TM 3-34.62 (30 May 2025 incl. C1, 29 Jul 2026), para 2-8
- 12N deep dive: What should an operator check before pushing over a large tree (12 to 30 inches)?
- Carefully probe for dead limbs that could fall, and determine the tree’s natural direction of lean—that is the best direction to push. Position the blade high and center it on the tree for maximum leverage.
- TM 3-34.62 (30 May 2025 incl. C1, 29 Jul 2026), para 2-9
- 12N deep dive: If a large tree has a massive, deeply embedded root system, what four-step method does TM 3-34.62 describe?
- Start on the side opposite the proposed fall and cut a V-ditch deep enough to sever some large roots, tilted downward toward the roots; cut sides two and three; then build an earth ramp on the same side as the original cut and push the tree over. Reverse quickly as it falls, and fill the stump hole so water does not collect.
- TM 3-34.62 (30 May 2025 incl. C1, 29 Jul 2026), para 2-9 and figure 2-4
- 12N deep dive: How long does it typically take a medium tractor to clear and pile a large tree?
- An average of 5 to 20 minutes per tree. Massive trees that need the four-step procedure often take more than 20 minutes each.
- TM 3-34.62 (30 May 2025 incl. C1, 29 Jul 2026), para 2-10
- 12N deep dive: How is a rake used on a dozer to remove roots and small stumps?
- Mount the rake in place of the blade. As the dozer moves forward, the teeth are forced below the surface, catching belowground roots and surface brush while soil remains or passes through.
- TM 3-34.62 (30 May 2025 incl. C1, 29 Jul 2026), para 2-11
- 12N deep dive: What safety precautions does TM 3-34.62 give for dozer clearing?
- Never operate clearing tractors too close together. Do not follow a falling tree too closely, because the stump and roots may catch under the front of the dozer. Clean accumulated debris out of the belly pan often to prevent fires in the engine compartment.
- TM 3-34.62 (30 May 2025 incl. C1, 29 Jul 2026), para 2-12
- 12N deep dive: What two methods are used to estimate production for clearing and grubbing?
- The quick method and the tree-count method. Use the quick method (table 2-1) only when a detailed reconnaissance and tree count are not feasible. The tree-count method allows a better estimate when a detailed reconnaissance is possible.
- TM 3-34.62 (30 May 2025 incl. C1, 29 Jul 2026), paras 2-13 through 2-15
- 12N deep dive: How do you convert a clearing area from square feet to acres?
- Divide the width in feet times the length in feet by 43,560 square feet per acre.
- TM 3-34.62 (30 May 2025 incl. C1, 29 Jul 2026), para 2-14, step 1
- 12N deep dive: In a well-managed earthmoving job, how many minutes of production time should you expect per hour?
- 50 minutes of production time per hour, because operators need breaks and there are always secondary delays for minor equipment repairs.
- TM 3-34.62 (30 May 2025 incl. C1, 29 Jul 2026), para 2-14, step 5
- 12N deep dive: What operator factors does table 2-2 list for track dozers?
- For a 60-minute working hour with good visibility: excellent 1.00 by day and 0.75 at night; average 0.75 by day and 0.56 at night; poor 0.60 by day and 0.45 at night.
- TM 3-34.62 (30 May 2025 incl. C1, 29 Jul 2026), para 2-14 and table 2-2
- 12N deep dive: Why is an angle blade preferred for sidehill cuts, and where should the cut start?
- Because of its side-casting ability, including when pioneering road cuts along hillsides. Start at the top of the hill and create a bench several dozer lengths long, beginning far enough up the slope to allow room for both the inner slope and the roadway. On extremely steep slopes, a winch line may be needed to stabilize the dozer.
- TM 3-34.62 (30 May 2025 incl. C1, 29 Jul 2026), paras 2-16 and 2-17 (winch note in para 2-17)
- 12N deep dive: After the initial sidehill bench is made, how should the roadway be shaped?
- Turn and work in the long direction of the project, get a full blade load, then turn to push material over the side. Keep the inside (hillside) of the roadway lower than the outside so the dozer can work the edge and reduce erosion of the outer slope, and maintain the proper inside slope because it is very hard to change later.
- TM 3-34.62 (30 May 2025 incl. C1, 29 Jul 2026), para 2-18 and figure 2-5
- 12N deep dive: What two methods does TM 3-34.62 describe for finishing a side slope with a dozer?
- Working perpendicular to the slope, starting at the top so earth falls to the lower side of the blade and forms a windrow used to fill holes; and working diagonally up the slope from the bottom, continually pushing the windrow to one side. The diagonal method is one of the few cases where a bulldozer is effective pushing uphill. Do not let the blade corner dig in too deep and steepen the slope beyond specifications.
- TM 3-34.62 (30 May 2025 incl. C1, 29 Jul 2026), paras 2-19 through 2-21 and figures 2-6 and 2-7
- 12N deep dive: When straight dozing, what should the operator do if the blade digs in or a heavy load slows the machine?
- If the blade digs in and the rear of the machine rises, raise the blade to continue an even cut. If a heavy load drops travel speed, shift to a lower gear and/or raise the blade slightly. When finishing or leveling, a full blade handles easier than a partially loaded blade.
- TM 3-34.62 (30 May 2025 incl. C1, 29 Jul 2026), para 2-23
- 12N deep dive: How much can side-by-side dozing increase production, and when is it not worth it?
- It can increase production by 15 to 25 percent when moving material 50 to 300 feet. If the distance is less than 50 feet, the extra time to maneuver and position the dozers offsets the increased production.
- TM 3-34.62 (30 May 2025 incl. C1, 29 Jul 2026), para 2-24 and figure 2-8
- 12N deep dive: What is slot dozing, and how much can it increase output?
- Use spillage from the first few passes to form a windrow on each side of the dozer’s path, creating a trench that prevents later blade spillage. Make cuts parallel, leave a narrow uncut section between slots, then doze that section out. When grade and soil conditions are favorable, output can increase by as much as 20 percent.
- TM 3-34.62 (30 May 2025 incl. C1, 29 Jul 2026), para 2-25 and figure 2-9
- 12N deep dive: How should a dozer push downhill to boost productivity?
- Stack multiple loads at the top of the hill, then push them all down in one go. When pushing downhill, go all the way to the bottom with each load. Push downhill whenever you can, because it boosts productivity.
- TM 3-34.62 (30 May 2025 incl. C1, 29 Jul 2026), para 2-26
- 12N deep dive: If rippers are not available, how can a dozer loosen hard or frozen material?
- Tilt the blade so one corner is forced into the material, hooking only the tilted end under it. A thin layer can also be broken by turning so the track grousers break through. For a thin frozen layer, break through at one point, then lift and push so the blade breaks the frozen crust.
- TM 3-34.62 (30 May 2025 incl. C1, 29 Jul 2026), para 2-27 and figure 2-10
- 12N deep dive: How should a dozer remove rocks, and how can track wear be reduced?
- Use a rake for small rocks so soil can pass through. For a large, partially buried boulder, tilt the blade, excavate earth from three sides, then get under the fourth side and raise the blade to lift and roll the boulder. Dozer work in rock increases track wear; install rock shoes or rock pads if possible.
- TM 3-34.62 (30 May 2025 incl. C1, 29 Jul 2026), para 2-28
- 12N deep dive: What special techniques apply when dozing wet or soft ground?
- Make each pass through the full depth of the wet material so the dozer has a more stable base, and use wider track shoes if possible to improve flotation. Push mud far enough that it does not flow back into the cut. Plan recovery operations in case the dozer gets stuck, and use a machine with a winch when you can.
- TM 3-34.62 (30 May 2025 incl. C1, 29 Jul 2026), para 2-29
- 12N deep dive: How can a dozer be used for ditching when a grader is not cutting the ditch?
- A grader is best for shallow ditches, but a dozer can do rough ditching. Tilt the blade to cut shallow V-ditches. For larger ditches, push material perpendicular to the ditch centerline, then, once the depth is reached, push along the length of the ditch to smooth the sides and bottom.
- TM 3-34.62 (30 May 2025 incl. C1, 29 Jul 2026), para 2-30 and figure 2-11
- 12N deep dive: What limits and warnings apply when a dozer is building a stockpile?
- On the first pass, push no more than 75 feet and do not excavate deeper than 6 to 8 inches, keeping a smooth cut. Begin raising the blade one dozer length from the stockpile so the material forms a ramp. Overlap cuts by about one-third of the blade width. Do not stop forward motion or spin the tracks while pushing. Before reversing, and while backing, the operator must be satisfied that no one will be endangered. Do not shift into neutral to coast downhill or change gears while going downhill.
- TM 3-34.62 (30 May 2025 incl. C1, 29 Jul 2026), para 2-31 (including the warning and caution)
- 12N deep dive: How should a dozer spread a large stockpile?
- Work from the side, cutting with only one-third of the blade, and keep working to the same side. Fill the blade without stalling or spinning the tracks, then spread by moving forward and slowly raising the blade until the load is evenly feathered. Raise the blade about 12 inches, back to the pile, and repeat. Do not back-blade to level the stockpile. If the material is higher than the midpoint of the ROPS, adjust the cut height so collapsing material is not a danger.
- TM 3-34.62 (30 May 2025 incl. C1, 29 Jul 2026), para 2-32
- 12N deep dive: How should a dozer backfill an excavation?
- An angle blade is most effective, pushing material sideways so the dozer can travel parallel to the excavation. With a straight blade, approach at a slight angle and turn in at the end of the pass. Keep the tracks from hanging over the edge. In soft material or on unstable slopes, let the second bladeful push the first over the edge. Keep oversize materials out of the backfill.
- TM 3-34.62 (30 May 2025 incl. C1, 29 Jul 2026), para 2-33
- 12N deep dive: What are the basic rules for dozer ripping?
- Use first gear. For one-shank ripping, always use the center shank, and use additional shanks when possible to increase production. Rip in the same direction the scrapers will load, if feasible, and generally rip as deeply as possible, or in natural layers if that is better. Place ripped material on top of the unripped formation to cushion the machine and provide traction. Cross-rip only when necessary. Never turn the dozer with the rippers in the ground, because that will damage the machine.
- TM 3-34.62 (30 May 2025 incl. C1, 29 Jul 2026), para 2-34 and figure 2-12
- 12N deep dive: How many ripper shanks should be used in different materials?
- Use as many shanks as possible, including three-shank ripping, when the material and desired size allow it. Use two shanks in areas with small rocks, and switch to the center shank if the machine stalls or the tracks spin. Raise the shank to lift out and break asphalt. Use one-shank ripping to sever reinforcing rods or wire mesh in concrete, and use one shank in hard-to-rip material or material that breaks out in large slabs.
- TM 3-34.62 (30 May 2025 incl. C1, 29 Jul 2026), paras 2-35 through 2-37
- 12N deep dive: What winch safety rules apply when a dozer is winching?
- Keep personnel clear of the cable, because a broken cable can cause severe injury. Keep the winch cable in a straight line behind the machine. Decelerate the engine before moving the winch control lever. When the machine is stationary, operate winch loads at low engine speed; when moving away from a load, use low gear. Do not operate the winch for extended periods. If engine speed is too low, a suspended load may drop even if the winch is in the reel-in position.
- TM 3-34.62 (30 May 2025 incl. C1, 29 Jul 2026), para 2-38 (including the caution)
- 12N deep dive: What assumed conditions are built into the TM 3-34.62 dozer production curves?
- A 60-minute working hour (100 percent efficiency); power-shift machines with 0.05-minute fixed times; the dozer cuts 50 feet, then drifts the blade load to dump over a high wall; soil density of 2,300 pounds per LCY; a coefficient of traction of 0.5 or better for crawlers and 0.4 or better for wheel machines; and hydraulic-controlled blades. Values are given in loose cubic meters or loose cubic yards per hour for straight and semi-universal blades.
- TM 3-34.62 (30 May 2025 incl. C1, 29 Jul 2026), para 2-39
- 12N deep dive: What material-type correction factors does table 2-4 list for crawler-dozer production?
- Loose, stockpile material is 1.2. Hard-to-cut or frozen material is 0.8 with a tilt cylinder and 0.7 without one. Hard-to-drift dead (dry, noncohesive) or very sticky material is 0.8. Ripped or blasted rock is 0.6 to 0.8. A production factor of 1 applies when the blade can cut the material and give it a rolling effect.
- TM 3-34.62 (30 May 2025 incl. C1, 29 Jul 2026), table 2-4 (in the dozer production-estimating steps after para 2-39)
- 12N deep dive: What operating-technique correction factors does table 2-5 list for crawler dozers?
- Slot dozing is 1.2. Side-by-side dozing is 1.15 to 1.25.
- TM 3-34.62 (30 May 2025 incl. C1, 29 Jul 2026), table 2-5 (in the dozer production-estimating steps after para 2-39)
- 12N deep dive: What is the key to successful ripping, regardless of seismic velocity?
- Tooth penetration, especially in homogeneous materials such as mudstone, clay stone, and fine-grained caliches.
- TM 3-34.62 (30 May 2025 incl. C1, 29 Jul 2026), para 2-50
- 12N deep dive: What assumptions underlie the ripping-production chart in figure 2-17?
- 100 percent efficiency (a 60-minute working hour); power-shift machines with single-shank rippers; the machine rips full-time, with no dozing. The upper limit of the band is for ideal conditions only; if thick or vertical laminations or other adverse rock structure exist, use the lower limit.
- TM 3-34.62 (30 May 2025 incl. C1, 29 Jul 2026), para 2-49
- 12N deep dive: What are the three basic operating parts of a scraper, and what does each do?
- The bowl is the loading and carrying component, with a cutting edge across the front bottom edge—lower it to load, raise it to carry, and lower it to the desired lift thickness to dump and spread. The apron is the front wall of the bowl; raise it to open for loading and spreading, and lower it during hauling to prevent spillage. The ejector is the rear wall; keep it to the rear when loading and hauling, and move it forward during spreading for a positive discharge of material.
- TM 3-34.62 (30 May 2025 incl. C1, 29 Jul 2026), para 3-1 and figure 3-2
- 12N deep dive: How do the Army 621G and 613B scrapers differ in how they load?
- The 621G is a single-powered-axle wheel scraper designed to load with a push tractor. The air-droppable 613B has a chain-elevator loading mechanism and can load without a push tractor. Pushing a 613 during loading will damage the loading elevator.
- TM 3-34.62 (30 May 2025 incl. C1, 29 Jul 2026), paras 3-1 and 3-6
- 12N deep dive: What are struck and heaped scraper capacities, and what ratings does the Army list for the 621G and 613B?
- Struck capacity is a level-full bowl; heaped capacity is material heaped in the bowl and sloping down on a 1:1 repose slope to the sides. Scraper loads are typically measured in LCY. The 621G is rated at 15.7 cubic yards struck and 22 cubic yards heaped. The 613B is rated at 11 cubic yards heaped; elevating scrapers like the Army 613 do not have struck-capacity ratings.
- TM 3-34.62 (30 May 2025 incl. C1, 29 Jul 2026), para 3-2
- 12N deep dive: What is the optimum haul distance for small- and medium-size scrapers?
- 300 to 3,000 feet. Larger scrapers can be effective up to 5,000 feet.
- TM 3-34.62 (30 May 2025 incl. C1, 29 Jul 2026), para 3-3
- 12N deep dive: Why is a scraper described as a compromise between a loader and a hauler?
- It is designed for medium-distance movement of materials. It is more efficient than a dozer because of its travel-speed advantage, and faster than a truck, with a typical load time of less than a minute. It can also spread its own load and quickly complete the dump cycle.
- TM 3-34.62 (30 May 2025 incl. C1, 29 Jul 2026), para 3-4
- 12N deep dive: What six operations make up a scraper production cycle?
- Loading, haul travel, dumping and spreading, turning at the dump site, return travel, and turning and positioning to load.
- TM 3-34.62 (30 May 2025 incl. C1, 29 Jul 2026), para 3-5
- 12N deep dive: What loading rules apply to a 621G scraper working with a push tractor?
- Use pusher assistance to reduce loading time and wheel spinning and to increase tire life, but do not rely on the pusher to do all the work, and do not spin the scraper wheels to pull away from the pusher. Use pusher assistance for straight, downhill, or straddle loading. Always load in the direction of haul, and avoid turning the scraper while it is accelerating out of the cut.
- TM 3-34.62 (30 May 2025 incl. C1, 29 Jul 2026), para 3-6
- 12N deep dive: Why is downhill scraper loading advantageous?
- It lets a scraper obtain larger loads in less time. Each 1 percent of favorable grade is equivalent to increasing the loading force by 20 pounds per ton of gross scraper weight.
- TM 3-34.62 (30 May 2025 incl. C1, 29 Jul 2026), para 3-7
- 12N deep dive: How does straddle loading work, and what time savings does it provide?
- Make two parallel cuts, leaving a ridge no wider than the distance between the scraper wheels, then make a final cut straddling that ridge. The center strip loads with less resistance than a full cut, so time is saved on every third trip.
- TM 3-34.62 (30 May 2025 incl. C1, 29 Jul 2026), para 3-8 and figure 3-3
- 12N deep dive: What are the back-track, chain, and shuttle push-loading techniques?
- Back-track is used when it is impractical to load in both directions, but it is inefficient because of the time spent backing and repositioning. Chain is used on a fairly long cut: the pusher pushes one scraper, then moves behind another scraper going the same direction in an adjacent lane, picking up two or more loads without backtracking. Shuttle is used on short cuts that can be loaded in both directions: the pusher pushes one scraper, then turns and pushes a second scraper in the opposite direction.
- TM 3-34.62 (30 May 2025 incl. C1, 29 Jul 2026), paras 3-9 through 3-11 and figure 3-4
- 12N deep dive: In the scraper cut-and-load sequence, how should the operator enter the cut and set the depth?
- Reduce travel speed with the service brake near the loading lane and downshift to first gear. Move the ejector to the rear, open the apron partway, and lower the bowl to an efficient cut depth after entering the cut. If the scraper tires spin before the dozer contacts the scraper, stop and wait for the dozer. The cut should be as deep as possible while still letting the scraper move at a constant speed without lugging the engine or slipping the drive wheels. Use the router bits on the vertical side of the bowl to gauge depth, and use that same depth on successive passes. Do not overload the scraper.
- TM 3-34.62 (30 May 2025 incl. C1, 29 Jul 2026), para 3-12
- 12N deep dive: What specific dozer-operator safety precautions does TM 3-34.62 list at the end of the dozer chapter?
- Never carry personnel on the tractor drawbar. Never turn around on a steep slope—back up or down instead. Keep the machine in low gear when towing a heavy load downhill. Always lower the attachments when the machine is parked. Ensure that only one person is on the machine while it is in operation.
- TM 3-34.62 (30 May 2025 incl. C1, 29 Jul 2026), para 2-52
- 12N deep dive: How should a scraper be loaded in loam or clay versus sand versus rock or shale?
- Loam and most clay soils cut easily and rapidly; very hard clay should be loosened with a dozer ripper first. For sand, which has little cohesion and tends to run ahead of the blade, enter the cut fast, lower the bowl slowly to fill the rear of the bowl, then shift down and use the pusher, pump the bowl up and down, and drop it sharply two or three times at the end of the cut to top out the load. For rock and shale, rip the material first, with the rip depth greater than the scraper cut depth, because loading unripped rock and shale is hard on the equipment.
- TM 3-34.62 (30 May 2025 incl. C1, 29 Jul 2026), para 3-13 and figure 3-5
- 12N deep dive: How long should push-loading a scraper take, and why is extra loading time usually not worthwhile?
- Ideally, push loading should take less than one minute over a distance of about 100 feet, though the exact values depend on the material. Studies show that about 85 percent of the scraper’s load capacity is reached in the first 0.5 minute; another 0.5 minute adds only about 12 percent more volume. Loading beyond one minute usually lowers production because total cycle time increases.
- TM 3-34.62 (30 May 2025 incl. C1, 29 Jul 2026), para 3-14
- 12N deep dive: What two borrow-pit practices help keep scraper support units productive?
- Traffic control in the borrow pit to minimize waiting time and unnecessary travel, and proper drainage maintenance throughout the pit to decrease downtime from inclement weather. The work requires highly competent personnel.
- TM 3-34.62 (30 May 2025 incl. C1, 29 Jul 2026), para 3-15
- 12N deep dive: How should scraper haul routes be laid out?
- Eliminate unnecessary maneuvering, and plan the job to avoid adverse grades that could drastically reduce production. Where grades permit, the shortest distance between two points is a straight line.
- TM 3-34.62 (30 May 2025 incl. C1, 29 Jul 2026), para 3-17
- 12N deep dive: How should scraper haul roads be maintained?
- Keep them in good condition so travel can be faster, safer, and less fatiguing, with less equipment wear. Use a grader or dozer to remove ruts and rough (washboard) surfaces. Use water distributors to reduce dust—less dust means less mechanical wear, better visibility, and fewer accidents. Keep roads moist, but not wet, so they pack into a hard, smooth surface.
- TM 3-34.62 (30 May 2025 incl. C1, 29 Jul 2026), para 3-18
- 12N deep dive: What travel rules should a scraper operator follow on the haul road?
- Use the highest safe gear for the road conditions. Keep the bowl relatively close to the ground, about 18 inches, to lower the center of gravity and reduce the risk of overturning. Avoid unnecessary engine lugging—downshift when losing momentum, because lugging lowers rpm and hydraulic pressure and can cause a loss of steering control. Never coast on a downgrade; slow down, downshift, and use transmission hold to prevent unwanted upshifting. Control speed on a downgrade with the retarder and service brakes, and do not exceed the manufacturer’s recommended engine rpm.
- TM 3-34.62 (30 May 2025 incl. C1, 29 Jul 2026), para 3-19
- 12N deep dive: What is the basic scraper dumping procedure and spreading sequence?
- Lower the bowl to the desired lift height, open the apron fully at the start of the dump, move the ejector forward, keep a straight path and a constant speed, then close the apron, return the ejector, and raise the bowl 12 to 18 inches for the return. Dump the first load at the front of the fill, travel over previous shallow lifts, start each following dump at the end of the previous fill, and finish one full lane so rollers can start compaction before opening a new lane. Do not waste time on the fill.
- TM 3-34.62 (30 May 2025 incl. C1, 29 Jul 2026), para 3-20
- 12N deep dive: How should a scraper fill be kept from sliding over the slope?
- Make the fill high on the outside edges so the scraper does not slide over the slope and damage it. If it rains, build up the low center for drainage, or use a grader to cut the outside edge down and crown the middle of the area.
- TM 3-34.62 (30 May 2025 incl. C1, 29 Jul 2026), para 3-21
- 12N deep dive: How should sand or wet, sticky material be dumped and spread from a scraper?
- Spread sand as thin as possible for better compaction and easier travel over the fill. For wet or sticky material, do not spread too thin; keep the bowl high enough for the material to pass under the scraper (or it will roll up into a solid mass that is hard to eject); bring the ejector forward about 12 inches at a time, then back it about 6 inches to break the suction, and repeat until the bowl is empty.
- TM 3-34.62 (30 May 2025 incl. C1, 29 Jul 2026), para 3-22
- 12N deep dive: In the TM 3-34.62 example, what is the load weight of 20 LCY of dry loam in a 621G scraper?
- Using an average dry-loam unit weight of 2,050 pounds per LCY (from the 1,900-to-2,200 range in table 1-2), the load weighs 20.5 tons (20 × 2,050 ÷ 2,000).
- TM 3-34.62 (30 May 2025 incl. C1, 29 Jul 2026), para 3-24 and table 1-2
- 12N deep dive: How is scraper rolling resistance calculated, and what representative values does table 3-2 list?
- Rolling resistance in pounds equals (40 + [30 × tire penetration in inches]) × the vehicle weight in tons. The 40 pounds per ton accounts for flexing of the driving mechanism, and the 30 pounds per ton per inch accounts for climbing out of the rut. Table 3-2 lists about 40 pounds per ton on a hard, smooth surface with no tire penetration; 65 on a firm, smooth surface that flexes slightly; 100 on a flexible dirt road with about 1 inch of penetration; 150 with up to 4 inches; and 220 to 400 on a soft, muddy road or sand with more than 6 inches of penetration.
- TM 3-34.62 (30 May 2025 incl. C1, 29 Jul 2026), paras 3-25 and 3-26 and table 3-2
- 12N deep dive: How are grade resistance and grade assistance calculated for a scraper?
- Grade resistance is the force that opposes a vehicle moving uphill; grade assistance helps it move downhill. The force in pounds equals 20 times the percent grade times the vehicle weight in tons. Uphill (adverse) grades are positive and require more power to overcome both rolling and grade resistance; downhill (favorable) grades are negative.
- TM 3-34.62 (30 May 2025 incl. C1, 29 Jul 2026), para 3-26 (step 4) and para 3-27
- 12N deep dive: What is rimpull required, and how does it compare with available rimpull?
- Rimpull required is the force, in pounds, needed to overcome rolling resistance and grade assistance or grade resistance (rimpull required = rolling resistance + grade assistance or grade resistance). Available rimpull is the maximum force the vehicle’s traction can handle. Required rimpull must always be less than available rimpull to avoid tire slippage.
- TM 3-34.62 (30 May 2025 incl. C1, 29 Jul 2026), para 3-28
- 12N deep dive: If a computed scraper travel speed exceeds the unit SOP maximum, what travel speed should be used in the estimate?
- The travel time should be based on the unit’s maximum allowable SOP speed, not the higher computed speed.
- TM 3-34.62 (30 May 2025 incl. C1, 29 Jul 2026), para 3-29 note
- 12N deep dive: What average times does TM 3-34.62 use for scraper dumping and turning?
- For scrapers with a heaped capacity of less than 25 cubic yards, average dumping time is 0.3 minutes. Average turning time is 0.3 minutes in the cut and 0.21 minutes on the fill (slightly higher in the cut because of congestion and the need to position for loading). For both the 613B and the 621G, allow 0.81 minutes total for dumping, turning at the dump site, and turning at the load site. Loading time is the main variable; a good average for a 621G with a D8 or equivalent push tractor is 0.85 minutes, and a 621G with a D7 takes about 1 minute of pusher contact.
- TM 3-34.62 (30 May 2025 incl. C1, 29 Jul 2026), paras 3-30 and 3-34
- 12N deep dive: How are scraper trips per hour calculated, and what working hour should be used?
- Divide the working minutes per hour by the cycle time. On a well-managed scraper job, use about 50 minutes of productive time per hour. In a confined area such as a ditch, or on a narrow bridge-header embankment, use 45 minutes per hour.
- TM 3-34.62 (30 May 2025 incl. C1, 29 Jul 2026), para 3-31
- 12N deep dive: In the TM 3-34.62 example, what is the hourly production of a 621G in loam making 18.5 trips per hour with a 20-LCY average load?
- 370 LCY per hour (18.5 × 20), which converts to 296 BCY per hour using the loam conversion factor of 0.8 from table 1-1. To convert LCY production to BCY or CCY, multiply by the appropriate soil conversion factor.
- TM 3-34.62 (30 May 2025 incl. C1, 29 Jul 2026), paras 3-32 and 3-33 and table 1-1
- 12N deep dive: How long would it take three 621G scrapers, each producing 296 BCY per hour, to move 19,440 BCY?
- 22 hours. Total time in hours equals the total volume in BCY divided by (hourly production in BCY per hour times the number of scrapers). The same relationship can be rearranged to find the number of scrapers needed to finish in a set number of hours.
- TM 3-34.62 (30 May 2025 incl. C1, 29 Jul 2026), para 3-34
- 12N deep dive: How is push-tractor cycle time calculated, and how many 621G scrapers can one pusher support in the TM example?
- Push-tractor cycle time equals (1.4 × load time) + 0.25 minute. With a 1-minute load time, cycle time is 1.65 minutes. Dividing a 2.71-minute scraper cycle by 1.65 shows that one push tractor can support 1.64 scrapers. Self-loading scrapers such as the 613B do not need a push tractor.
- TM 3-34.62 (30 May 2025 incl. C1, 29 Jul 2026), paras 3-34 and 3-35
- 12N deep dive: Why must pusher cycle time be checked when one push tractor supports more than one scraper?
- The pusher cycle time may control production. In the TM example, one pusher with a 1.65-minute cycle supporting two 621Gs hauling 20 LCY of loam on a 50-minute hour produces 485 BCY per hour. If you incorrectly assumed the pusher could keep up with two scrapers on a 2.71-minute scraper cycle, you would overstate production at 590 BCY per hour.
- TM 3-34.62 (30 May 2025 incl. C1, 29 Jul 2026), para 3-36
- 12N deep dive: How many push tractors are required for nine 621G scrapers if one pusher can support 1.64 scrapers?
- Six push tractors (9 ÷ 1.64, rounded up to the whole number of tractors required).
- TM 3-34.62 (30 May 2025 incl. C1, 29 Jul 2026), para 3-37
- 12N deep dive: When using the dozer production curves, what equivalents should be used for the DEUCE and the medium crawler tractor (MCT)?
- The DEUCE has the same production capability as the D5 (use the D6T-through-D7E straight-blade curve in figure 2-13 as directed for that class). Marines should use D7 data as equivalent to the MCT.
- TM 3-34.62 (30 May 2025 incl. C1, 29 Jul 2026), dozer production-estimating steps after para 2-39, and figures 2-13 and 2-14
- 12N deep dive: Besides grading, shaping, bank sloping, and ditching, what else can a grader do, and what can it not do?
- Graders are also used for mixing, spreading, side casting, leveling, crowning, general construction, and road and runway maintenance, and they can move small amounts of material. They cannot perform dozer work because of the structural strength and location of their blade. They can work on slopes as steep as 3:1 and cut ditches to a depth of 3 feet.
- TM 3-34.62 (30 May 2025 incl. C1, 29 Jul 2026), ch. 4 introduction (immediately before the “Grader Components” heading)
- 12N deep dive: What are the main working components of a grader, and how is the blade adjusted?
- The blade and the scarifier. The blade’s position and pitch are adjustable and are set according to the operation. The primary part of the blade is a hydraulically controlled moldboard with bolted-on cutting edges. The ends of the blade can be raised or lowered together or independently, and the blade can be placed perpendicular or parallel to the direction of travel, shifted to either side, or raised vertically.
- TM 3-34.62 (30 May 2025 incl. C1, 29 Jul 2026), paras 4-1 through 4-3 and figures 4-1 through 4-3
- 12N deep dive: How does grader-blade pitch affect cutting versus dragging?
- Keep the blade near the center of the pitch adjustment so the top of the moldboard stays directly over the cutting edge. Pitched forward, cutting ability decreases and dragging increases—the blade tends to ride over the material, is less likely to catch on solid obstructions, and is ideal for light, rapid cuts and blending. Pitched to the rear, the blade cuts readily, but the material tends to boil over itself.
- TM 3-34.62 (30 May 2025 incl. C1, 29 Jul 2026), para 4-4 and figure 4-3
- 12N deep dive: How is a grader scarifier set up, and what tooth-removal limit applies?
- Use the scarifier to break up hard material the blade cannot cut. It has 11 removable teeth that can cut up to 12 inches deep. In hard material you may need to remove some teeth, but do not remove more than five, or the remaining teeth may shear off. Start with the center tooth and then alternate with the other four so the load stays balanced. With the top of the scarifier pitched to the rear, the teeth lift and tear the material; use that position for breaking up asphalt pavement.
- TM 3-34.62 (30 May 2025 incl. C1, 29 Jul 2026), para 4-5 and figure 4-1
- 12N deep dive: How should a grader start a ditch cut?
- First make a 3- to 4-inch-deep marking cut on the first pass at the outer edge of the bank slope, usually marked by slope stakes. Align the toe of the blade with the outside edge of the lead wheel so the mark guides later cuts and the ditch stays straighter. Then make each ditch cut as deep as possible without stalling or losing control, normally in second gear at full throttle. Start with the toe in line with the center of the lead wheel, and bring each successive cut in so the toe is in line with the ditch bottom on the final cut.
- TM 3-34.62 (30 May 2025 incl. C1, 29 Jul 2026), paras 4-7 and 4-8 and figures 4-4 and 4-5
- 12N deep dive: Why must the bank of a road-cut ditch be sloped, and how is the ditch then cleaned and finished?
- Sloping the bank prevents slope-sloughing failures, excessive erosion, and a ditch that fills up. Cast material from the outer slope into the ditch bottom and remove it later. To clean the ditch, put the blade in the same position used for ditching cuts so the material is cast onto the shoulder, then move that windrow onto the road while finishing the shoulder to the desired slope. Finally, spread the material on the roadway to the desired crown or cross slope.
- TM 3-34.62 (30 May 2025 incl. C1, 29 Jul 2026), paras 4-10 through 4-13 and figure 4-6
- 12N deep dive: How should a grader maintain an earth or gravel road or runway surface in dry weather?
- Work material across the surface from one side to the other to keep it smooth, but in dry weather move eroded material from the edges and shoulders toward the center. Be careful when disturbing a dry surface, because traffic or wind can cause the loss of binder. The surface is easier to work when it is damp, so do this maintenance after a rain or use a water truck to dampen dry material. On the pass, apply enough downward pressure to penetrate about 1/2 inch on a level plane.
- TM 3-34.62 (30 May 2025 incl. C1, 29 Jul 2026), para 4-14
- 12N deep dive: When is the best time to reshape an earth or gravel road, and what if the road is dry?
- After a rain, when binder is present and the moisture content is appropriate, so cut material can be spread over a smooth base and compact properly. If the road is dry, moisten it with a water distributor first.
- TM 3-34.62 (30 May 2025 incl. C1, 29 Jul 2026), para 4-15
- 12N deep dive: How should a grader correct a corrugated (washboard) road?
- Be careful not to make the problem worse. Deep cuts on a washboard surface can cause blade chatter and emphasize the corrugations. Severely corrugated surfaces may need to be scarified. With the right moisture content, change the blade angle so the cutting edge does not follow the rough surface, cut to the bottom of the corrugations, and spread the windrows evenly to reshape the road. Traffic will help compact it, but rolling after shaping gives better, longer-lasting results.
- TM 3-34.62 (30 May 2025 incl. C1, 29 Jul 2026), para 4-16
- 12N deep dive: How should a grader blade be set when removing snow from uneven pavement or a portable runway?
- Raise the blade 0.5 to 1 inch. Improper adjustment can damage the grader and may gouge the surface.
- TM 3-34.62 (30 May 2025 incl. C1, 29 Jul 2026), para 4-17
- 12N deep dive: How is mixed-in-place asphalt worked with a grader, and how is imported aggregate mixed?
- For mixed-in-place asphalt, spread the asphalt on the road before or after scarifying, then mix it with the surface soil by scarifying and/or windrowing with the blade. For imported aggregate, shape and prepare the base, dump the mix into uniform windrows (blade them to dry if too wet), flatten the windrow and apply asphalt, then mix by moving the windrow from side to side; several graders may work tandem on the same windrow. If rain moistens the mix, keep mixing until it is dry, then blade it back into a windrow before spreading.
- TM 3-34.62 (30 May 2025 incl. C1, 29 Jul 2026), paras 4-19 and 4-20
- 12N deep dive: How are blue-top hubs used when a grader spreads a mixture over a large area?
- Blue-top hubs (blue tops) mark the final pavement elevation. They are typically placed 20 feet apart in a grid pattern, and the edges of each windrow’s spread width are marked with stakes. Remove the blue tops before rolling. Usually one pass flattens the windrow, then it is spread to each side in increments to a uniform thickness with the proper slopes.
- TM 3-34.62 (30 May 2025 incl. C1, 29 Jul 2026), para 4-21
- 12N deep dive: How does a grader spread or level windrows compared with a dozer?
- If there is room, extend the blade and reduce the windrow with a series of side cuts. A grader has less power and traction than a dozer but moves the load faster. Its lower, more concave blade gives the load more rolling action, so a large quantity can be pushed without spilling over the top. Large windrows may take two or more side cuts.
- TM 3-34.62 (30 May 2025 incl. C1, 29 Jul 2026), para 4-23 and figures 4-7 and 4-8
- 12N deep dive: At what blade angle should a grader usually work a road, and which way is “zero” angle?
- To shape and maintain most roads, set the blade at a 25° to 30° angle so the load drifts off the trailing end. Decrease the angle for spreading windrows, and increase it for hard cuts and ditching. A blade set straight across (perpendicular to the direction of movement) is at 0°.
- TM 3-34.62 (30 May 2025 incl. C1, 29 Jul 2026), para 4-24 and figure 4-9
- 12N deep dive: How should a grader plane an irregular surface, and what should be kept off the rear wheels?
- Set the blade at an angle and use the cut material to fill hollows, always cutting enough to keep some material in front of the blade. Move loosened material forward and sideways to distribute it; on the next pass, pick up what was left at the trailing edge. On the final pass, make a lighter cut and lift the trailing edge enough for surplus material to go under the blade so a ridge is not left. Do not pile windrows in front of the rear wheels, because that hurts traction and control.
- TM 3-34.62 (30 May 2025 incl. C1, 29 Jul 2026), para 4-25
- 12N deep dive: What gear ranges does table 4-1 list for common grader operations under normal conditions?
- Maintenance, second to third; spreading, third to fourth; mixing, fourth to sixth; ditching, first to second; bank sloping, first; snow removal, fifth to sixth; and finishing, second to fourth. Operate as fast as the operator’s skill and road conditions permit, at full throttle in each gear; if less speed is needed, use a lower gear rather than part throttle.
- TM 3-34.62 (30 May 2025 incl. C1, 29 Jul 2026), para 4-26 and table 4-1
- 12N deep dive: What forward road speeds does table 4-2 list for the Army 120M grader at rated rpm?
- First 2.3 mph, second 3.7, third 5.9, fourth 9.7, fifth 15.5, and sixth 24.5. Reverse speeds are the same as the forward speeds.
- TM 3-34.62 (30 May 2025 incl. C1, 29 Jul 2026), para 4-26 and table 4-2
- 12N deep dive: When should a grader be backed up instead of turned around, and where should turns be avoided?
- When making multiple passes over a short distance (less than 1,000 feet), it is usually more efficient to back the grader to the starting point than to turn it around. Avoid making turns on a newly laid bituminous road or runway surface.
- TM 3-34.62 (30 May 2025 incl. C1, 29 Jul 2026), para 4-28
- 12N deep dive: Why must grader tires be properly inflated, and can a grader still work in mud?
- Overinflated tires reduce contact with the road and cause a loss of traction. Unequal rear-tire pressure can cause slippage and grader bucking; use the inflation pressure in the operator’s manual. Wet and muddy conditions reduce traction and efficiency, but the grader is still the best machine for those conditions—for example, it can effectively cast surface mud to the side on a haul road.
- TM 3-34.62 (30 May 2025 incl. C1, 29 Jul 2026), paras 4-30 and 4-31
- 12N deep dive: What is tandem grader operation, and why is it used on haul-road maintenance?
- Using enough graders to finish one side of a road with a single pass of each grader. Maintenance of one side is completed while the other side stays open to traffic. Tandem operation also expedites leveling, mixing, and spreading. Graders are the most suitable machines for keeping haul roads in good condition so scrapers or dump trucks stay efficient.
- TM 3-34.62 (30 May 2025 incl. C1, 29 Jul 2026), paras 4-32 and 4-33
- 12N deep dive: How is grader production calculated when it is measured as area covered per hour?
- In English units, hourly area A = S × (Le – Lo) × 5,280 × E, where S is speed in mph, Le is effective blade length in feet, Lo is width of overlap in feet, 5,280 is feet per mile, and E is job efficiency. The metric form uses 1,000 meters per kilometer. Because the moldboard is usually angled, effective blade length is shorter than the actual moldboard length as the angle increases (see table 4-5 and figure 4-10).
- TM 3-34.62 (30 May 2025 incl. C1, 29 Jul 2026), paras 4-34 and 4-36, figure 4-10, and table 4-5
- 12N deep dive: What operating speeds does table 4-4 list for common grader tasks?
- Finish grading 0–2.5 mph (0–4 km/hr); heavy blading 0–6 mph (0–9 km/hr); ditch repair and ripping 0–3 mph (0–5 km/hr); road maintenance and haul-road maintenance 3–9.5 mph (5–16 km/hr); snow plowing 4–13 mph (7–21 km/hr); and snow winging 9–17 mph (15–28 km/hr).
- TM 3-34.62 (30 May 2025 incl. C1, 29 Jul 2026), para 4-35 and table 4-4
- 12N deep dive: In the TM 3-34.62 example, what production does a 12-foot 120M grader achieve doing road maintenance at 8 mph with a 30° blade angle and 0.90 efficiency?
- 7.33 acres per hour (or 3.07 hectares per hour). Effective blade length at 30° is 10.4 feet (3.17 meters), minus 2.0 feet (0.6 meters) of overlap. Efficiency of 0.90 is used because long road-maintenance passes mean fewer turnabouts.
- TM 3-34.62 (30 May 2025 incl. C1, 29 Jul 2026), para 4-37 and table 4-5
- 12N deep dive: What specific safety rules does TM 3-34.62 list for grader operators?
- Display a red flag or a flashing light on a staff at least 6 feet above the left rear wheel when operating slowly on a highway or roadway. Never allow other personnel to ride on the blade or rear of the grader. Engage the clutch gently, especially uphill or pulling out of a ditch. Reduce speed before turning or applying the brakes. Keep the grader in low gear on steep downgrades. Drive slowly on hillsides and watch for holes or ditches. Never use a grader to pull stumps or other heavy loads. Keep the blade angled well under the machine when it is not in use. Never allow more than one person on a grader while it is in operation; if it has a buddy seat, no more than two people may be on the machine while it is operating.
- TM 3-34.62 (30 May 2025 incl. C1, 29 Jul 2026), para 4-39
12N – Deep Dive: Loaders, Excavators, Hauling, Compaction, Safety & Soils
Source: TM 3-34.62 (Earthmoving Operations, 30 May 2025 incl. C1, 29 Jul 2026); TM 3-34.64 (Military Soils Engineering, 25 Sep 2012). Complements mos-12n and mos-12n-3; does not repeat those cards. Verify current editions.
- 12N deep dive: How does TM 3-34.62 describe military wheel loaders, and what attachments are most common?
- They are diesel-driven, rubber-tired machines with a power-shift transmission and a torque converter, so they can move quickly forward and reverse with minimal shock and keep a high production rate. The hydraulic system gives precise control of attachments and also assists with steering. Most loaders have pintles or towing hooks for small trailers or light loads. The most common attachments are a shovel-type bucket or a forklift; hooks for sling loads and snowplows are also available.
- TM 3-34.62 (30 May 2025 incl. C1, 29 Jul 2026), paras 5-1 and 5-2 and figures 5-1 and 5-2
- 12N deep dive: How do general-purpose and multipurpose loader buckets differ?
- A general-purpose bucket is a one-piece conventional bucket. A multipurpose bucket is a two-piece hinged-jaw bucket that lets the loader work as a dozer and grab material, and it is better with sticky material. Buckets are heavy-duty all-welded steel, typically 2.5 to 5 cubic yards, connected by lift arms, with bolted or welded teeth on replaceable cutting edges. For medium materials, bolt-on replaceable teeth are provided.
- TM 3-34.62 (30 May 2025 incl. C1, 29 Jul 2026), paras 5-3 and 5-12
- 12N deep dive: What tasks is a loader commonly used for, and when is its production highest?
- Loading trucks, stockpiling, digging basements or gun emplacements, backfilling ditches, and lifting and moving construction materials; also stripping overburden, charging hoppers, moving forms and pipe, assisting with plant work, and towing light loads. With rock-tread tires it can work in and around quarries. Production is highest on a flat, smooth surface with enough room to maneuver. Loaders work well in soft to medium-hard material, but production drops in medium to hard material, and the loader must be able to dump over the side of a truck bed.
- TM 3-34.62 (30 May 2025 incl. C1, 29 Jul 2026), paras 5-5 and 5-6
- 12N deep dive: How should a loader bucket be loaded on the forward pass?
- Keep the bucket parallel to the ground so the cutting edge skims the travel surface and removes ruts, obstacles, and loose material. When the edge contacts the bank or stockpile, move forward slowly with more power, raise the bucket while penetrating, crowd the material in, and roll the bucket back to prevent spilling. Keep the bucket up while backing away so the load does not spill.
- TM 3-34.62 (30 May 2025 incl. C1, 29 Jul 2026), para 5-7
- 12N deep dive: What is the V-loading method for loading trucks with a single loader?
- Approach the bank or stockpile in low gear with the bucket 1 to 2 inches off the ground, fill and fully roll back the bucket without spinning the tires, back away, then approach the haul unit at a 90° angle, lifting the bucket high enough to clear it. Do not touch the haul unit with the front tires or the bucket. Dump by rolling the bucket slowly forward, then back away while lowering and leveling the bucket. Best production comes from keeping both the angle of turn and the travel distance to a minimum.
- TM 3-34.62 (30 May 2025 incl. C1, 29 Jul 2026), paras 5-8 and 5-9 and figure 5-3
- 12N deep dive: How is clam loading done with a multipurpose bucket, and how high should the load be carried?
- Center the bucket on the load, begin opening it about 5 feet away, penetrate about two-thirds of the opened bucket into the material, close the bucket, and carry the load 10 to 14 inches above the ground. Keep the bucket as low as possible for better balance and visibility, and travel at low speed over rough terrain. Open the bucket fully to dump, raise it to clear previously dumped material, then close it and return to the 10- to 14-inch travel position.
- TM 3-34.62 (30 May 2025 incl. C1, 29 Jul 2026), para 5-10 (including the caution)
- 12N deep dive: How should a loader dig a basement or gun emplacement?
- First build a ramp into the excavation so the loader can excavate above wheel level (the way it works best) and later exit with the material. Pitch the bucket forward, move forward and gradually penetrate by lowering the lift control, stay in as high a gear as possible without excessive tire spin, retract the bucket fully, raise it to clear the area, and dump onto a stockpile or into a haul unit. First break or loosen medium to hard material.
- TM 3-34.62 (30 May 2025 incl. C1, 29 Jul 2026), paras 5-11 and 5-12 and figure 5-4
- 12N deep dive: How should a loader backfill a trench?
- Lower the bucket to ground level and use the machine’s forward movement to push piled earth into the trench. This works best when the bucket is as wide as, or wider than, the wheels or tracks; a narrow bucket can let the wheels ride up the pile and raise one corner. Approach a stockpile at a 45° angle so one-third of the bucket contacts it (work from the edges on a large pile), keep the bucket just off natural ground, and do not spin the tires. For a large stockpile, work from the edges.
- TM 3-34.62 (30 May 2025 incl. C1, 29 Jul 2026), para 5-13 and figure 5-5
- 12N deep dive: What bucket fill factors does table 5-1 list for wheel loaders?
- As a decimal of heaped-bucket capacity, adjusted to LCY: mixed moist aggregates and uniform aggregates up to 1/8 inch, 0.95 to 1.00; 1/8- to 3/8-inch aggregates, 0.90 to 0.95; 1/2-inch and larger, 0.85 to 0.90; well-blasted rock, 0.80 to 0.95; average blasted rock, 0.75 to 0.90; poorly blasted rock, 0.60 to 0.75; rock-dirt mixtures, 1.00 to 1.20; moist loam, 1.00 to 1.10; and soil, 0.80 to 1.00.
- TM 3-34.62 (30 May 2025 incl. C1, 29 Jul 2026), para 5-15 and table 5-1
- 12N deep dive: What average cycle times does table 5-2 list for wheel loaders?
- 0.45 to 0.50 minutes for a 1.00- to 3.75-cubic-yard heaped bucket, and 0.50 to 0.55 minutes for a 4.00- to 5.50-cubic-yard bucket. Those times include load, maneuver with four reversals of direction (minimum travel), and dump, with no extra travel required.
- TM 3-34.62 (30 May 2025 incl. C1, 29 Jul 2026), para 5-15 and table 5-2
- 12N deep dive: In the TM 3-34.62 example, what is the net production in tons per hour of a wheel loader working in loam at 263 LCY per hour?
- 289 tons per hour. Loam at 2,200 pounds per LCY is 1.1 tons per LCY (2,200 ÷ 2,000), and 263 × 1.1 = 289. In general, tons per hour equals LCY per hour times the material weight in tons per LCY.
- TM 3-34.62 (30 May 2025 incl. C1, 29 Jul 2026), paras 5-17 and 5-18
- 12N deep dive: What safety practices does TM 3-34.62 list for wheel-loader operators?
- Operate carefully because wheel loaders are easy to overturn. Do not extend any part of your body between the cab and the lift arms. Block the bucket when working on the machine. Use caution when removing and replacing lock rings. Do not work between the wheels and the frame while the engine is running. Use caution near a trench edge or under overhangs created by digging into banks or stockpiles. Travel with the bucket at or below axle height. Do not carry or lift personnel in the bucket. Ground the bucket and set the parking brake before leaving the machine.
- TM 3-34.62 (30 May 2025 incl. C1, 29 Jul 2026), para 5-19
- 12N deep dive: What makes a hydraulic excavator or backhoe loader useful for digging below the machine?
- Hydraulic excavators have fast-acting, variable-flow hydraulics and high breakout force, and a wide choice of booms, sticks, buckets, and attachments for trench excavation, truck loading, ditch cleaning, concrete breaking, and pipe installation. The hydraulic hoe is especially effective for digging below the surface where the machine sits. The backhoe loader (BHL) is well suited to confined spaces and has good mobility.
- TM 3-34.62 (30 May 2025 incl. C1, 29 Jul 2026), para 8-1 and figure 8-1
- 12N deep dive: What two trenching methods does TM 3-34.62 describe for a backhoe loader?
- Parallel and perpendicular. In the parallel method, position the BHL directly over the trench, keep the tractor aligned with the trench centerline, and gradually move the machine away as digging continues; spoil may go into haul units or be stockpiled along the side for backfill. In the perpendicular method, dig the trench in two or more lifts: excavate the top 35 to 45 percent of the depth with the boom high, then move forward about half the machine’s length and lower the boom to finish the cut. That gives better bucket digging angles and reduces the hoisting distance for the upper lifts.
- TM 3-34.62 (30 May 2025 incl. C1, 29 Jul 2026), paras 8-3 through 8-5 and figure 8-3
- 12N deep dive: How should a BHL excavate a basement, and when should service-pipe trenches be dug?
- First cut a trench with vertical outside walls, and keep all exterior wall faces vertical to reduce manual cleanup. Plan the starting point and digging sequence so the machine can exit efficiently when the work is done. Dig trenches for service pipes last, working from the basement outward. Position the machine above the outer edge and dig toward the end and sides of the tractor.
- TM 3-34.62 (30 May 2025 incl. C1, 29 Jul 2026), para 8-6 and figure 8-4
- 12N deep dive: What should be done before a hoe starts digging, and how should ditch work be started in wet areas?
- Survey the area for underground hazards and surface obstacles before digging, especially in populated areas with underground utilities. If the job will continue in wet seasons or wet areas, give prime consideration to drainage: begin ditch excavations at the lower end and work toward the upgrade. Working in confined quarters is inefficient, so plan to use small machines with a minimum work radius when close-quarter work is expected.
- TM 3-34.62 (30 May 2025 incl. C1, 29 Jul 2026), paras 8-7 through 8-9
- 12N deep dive: How should a hoe deal with hardpan or layered rock in a trench?
- A hoe can dig fairly hard materials, but blasting or ripping may be more efficient than breaking hardpan and rock with the bucket. Once the trench is open, break ledge rock by positioning the bucket underneath the layers and pulling it upward. Remove the top layers first, lifting only one or two layers at a time.
- TM 3-34.62 (30 May 2025 incl. C1, 29 Jul 2026), para 8-10
- 12N deep dive: How must a BHL be set before the backhoe is operated, and what average excavation cycle times apply?
- Level the hoe before operating it. Lower the front loader bucket flat to the ground so the front wheels are off the surface, shift the gear and range levers to neutral, lower the outriggers, and use them to level the machine and raise the rear wheels slightly off the ground. Always operate with minimal bucket-arm swing. Under average conditions (cut depth 40 to 60 percent of rated maximum digging depth and a 30° to 60° swing), a small excavator with a bucket of less than 1 cubic yard can complete a cycle—load, swing loaded, dump, and swing empty—in 14 seconds; buckets from 1 to less than 2.5 cubic yards average 15 seconds. Greater depth or a wider swing increases cycle time.
- TM 3-34.62 (30 May 2025 incl. C1, 29 Jul 2026), paras 8-12 and 8-13
- 12N deep dive: What hoe-bucket fill factors does table 8-1 list?
- Hoe buckets are rated for heaped capacity at an assumed 1:1 repose angle, so actual capacity varies with the material. Fill factors are 100 to 110 percent for moist loam or sandy clay; 95 to 110 percent for sand and gravel; 40 to 50 percent for poorly blasted rock; 60 to 75 percent for well-blasted rock; and 80 to 90 percent for hard, tough clay.
- TM 3-34.62 (30 May 2025 incl. C1, 29 Jul 2026), para 8-14 and table 8-1
- 12N deep dive: What is the optimum depth of cut for a hoe, and how is the dipper cylinder used to dig?
- As a rule, the optimum depth of cut is 30 to 60 percent of the machine’s maximum digging depth. Maximum digging force is developed when the dipper cylinder is operated perpendicular to the dipper. Lower the bucket, roll it until the teeth or cutting edge is flat on the ground, use the stick cylinder to move the bucket toward the machine until it is half full, then raise the stick and roll the bucket until it is full.
- TM 3-34.62 (30 May 2025 incl. C1, 29 Jul 2026), para 8-16 and figures 8-2 and 8-6
- 12N deep dive: How can spotting a dump truck save hoe loading time?
- If feasible, position the truck on the pit floor so that when digging is complete the bucket is already above the haul unit and does not have to be raised further before swinging and dumping. That setup can save about 12 percent of the total excavation-loading cycle time. Spot the truck so the hoe does not have to turn more than 90°, rotate the bucket over the rear of the dump bed rather than over the cab, raise the bucket while moving toward the truck and lower it while moving away, and shake the bucket only when necessary to loosen stuck dirt.
- TM 3-34.62 (30 May 2025 incl. C1, 29 Jul 2026), para 8-18
- 12N deep dive: How should a BHL loader bucket be used to backfill a trench?
- Position the machine at about a 45° angle to the trench and spoil pile. With the bucket about 2 inches above natural ground, use it like a dozer blade to push material into the trench; keep the bucket level and do not crowd or curl. After the material falls in, reverse and move along the pile to repeat. Dump whatever remains in the bucket on the last pass. If the spoil pile is higher than 2 feet or is wet, take it in two passes—the upper half first, then a cleanup pass.
- TM 3-34.62 (30 May 2025 incl. C1, 29 Jul 2026), para 8-20
- 12N deep dive: What are the basic capabilities of a track-mounted excavator in TM 3-34.62?
- It is a diesel-powered machine with a maximum digging depth of about 20 feet and a dumping height of about 22 feet. It can travel around a job site at a maximum of 3 mph in high range, but must be transported for long-distance moves. Common uses include excavating pipeline trenches, drainage ditches, and building footings; creating hasty fortifications; and loading trucks. Buckets range from 1 to 2.5 cubic yards, and under average conditions (an 8- to 12-foot cut and a 30° to 60° swing) the excavation cycle is about 15 seconds.
- TM 3-34.62 (30 May 2025 incl. C1, 29 Jul 2026), paras 8-21 and 8-22 and figure 8-8
- 12N deep dive: How much more can an excavator lift over the front than over the side, and what planning is required?
- Lifting capacity is 65 to 70 percent greater when lifting over the front of the machine than over the side. The weight it can lift depends on the distance of the load from the machine’s center of gravity, so consult the current specification sheets before any lift and position the excavator as close to the load as possible. These machines are designed to handle loads of up to 15,000 pounds at a 15-foot swing radius from the side.
- TM 3-34.62 (30 May 2025 incl. C1, 29 Jul 2026), para 8-23
- 12N deep dive: In the TM 3-34.62 hoe example, what ideal production does a 0.25-cubic-yard bucket in hard clay achieve?
- 55 LCY per hour. The example uses an 85 percent fill factor (the midpoint of the 80-to-90 percent range for hard, tough clay), a 14-second average cycle, and the formula: 3,600 seconds per hour times bucket size times fill factor, divided by cycle time in seconds (3,600 × 0.25 × 0.85 ÷ 14). That ideal rate is then multiplied by the job-efficiency factor (for example, 50/60 for a 50-minute working hour).
- TM 3-34.62 (30 May 2025 incl. C1, 29 Jul 2026), paras 8-12, 8-14, and 8-25 and table 8-1
- 12N deep dive: How is dump-truck hauling capacity measured, and what Army truck sizes does TM 3-34.62 focus on?
- Capacity may be measured gravimetrically by the weight of the load in tons, by struck rear-dump body volume in cubic yards, or by heaped rear-dump body capacity in cubic yards. Army dump-truck capacity is typically expressed gravimetrically, such as 5-ton (FMTV) and 20-ton. Always ensure that the volumetric load does not exceed the truck’s gravimetric capacity. Material unit weights can range from as low as 1,700 pounds per LCY for dry clay to as high as 3,500 pounds per LCY for trap rock.
- TM 3-34.62 (30 May 2025 incl. C1, 29 Jul 2026), paras 10-1 and 10-2, figures 10-1 and 10-2, and table 1-2
- 12N deep dive: How full should dump trucks be loaded, and why must overloading be avoided?
- Load trucks as close to their rated hauling capacity as possible, but reduce the load if haul roads are in poor condition or the trucks must navigate steep grades. Overloading causes higher fuel consumption, decreased tire life, and increased mechanical failures.
- TM 3-34.62 (30 May 2025 incl. C1, 29 Jul 2026), para 10-3
- 12N deep dive: How should trucks be spotted for loading, and what V-position is used with a loader?
- Use spotting markers when loading from a hopper, grizzly ramp, or stockpile, and also when excavators such as draglines, clamshells, loaders, backhoes, or hoes are loading the trucks; markers improve speed and accuracy. When loading with an excavator, keep trucks as close to the bank as possible and within the working radius of the bucket. When using a loader, arrange the truck and loader in a V shape to reduce the loader’s cycle time.
- TM 3-34.62 (30 May 2025 incl. C1, 29 Jul 2026), paras 10-4 and 10-5 and figure 10-3
- 12N deep dive: What speed and haul-road practices should a dump-truck operation use?
- Transport materials at the highest safe speed in the appropriate gear; do not speed. When several trucks are working, keep a consistent speed so loading and dumping points do not bottleneck. If possible, use separate haul roads to and from the dump site, keep the roads well maintained, minimize the grade, and use one-way traffic patterns.
- TM 3-34.62 (30 May 2025 incl. C1, 29 Jul 2026), para 10-6
- 12N deep dive: How should a dump truck unload material that must be spread, and how should dump bodies be maintained?
- Use a spotter, and when the material must be spread, move the truck slowly forward while dumping. Establish alternative dumping locations to keep proper spacing if poor footing or difficult spotting slows the work. Keep truck bodies clean—rust, dirt, dried concrete, or bituminous material hinders production. Clean bodies thoroughly at the end of the day; when hauling wet concrete, spray the bed with water before loading and clean it soon after dumping; when hauling plant-mix asphalt, coat the body with diesel fuel or oil so the mix does not stick.
- TM 3-34.62 (30 May 2025 incl. C1, 29 Jul 2026), paras 10-7 and 10-8
- 12N deep dive: How do you estimate the number of dump trucks needed to keep a loader working at capacity?
- Number of trucks required = 1 + (truck cycle time ÷ loader cycle time). The “1” is a safety factor so that, if operations stay on schedule, one truck is always standing by at the loader ready for spotting. Truck cycle time is the time to travel loaded to the dump, unload, return, and be reloaded. Loader cycle time is the time to load the truck plus any time lost waiting for the truck to be spotted. After work starts, the number needed may change with haul-road conditions, haul length, or conditions at the loading or unloading areas.
- TM 3-34.62 (30 May 2025 incl. C1, 29 Jul 2026), paras 10-9 and 10-10
- 12N deep dive: How many standby dump trucks should be planned?
- It depends on the mechanical condition of the active trucks and on the size and importance of the job. For smaller fleets with a single loading unit, the ratio of standby trucks to active trucks could be as high as 1:4; on larger jobs the ratio tends to be smaller. Standby trucks do not have to sit idle—they can be used on lower-priority tasks from which they can be redirected if needed.
- TM 3-34.62 (30 May 2025 incl. C1, 29 Jul 2026), para 10-11
- 12N deep dive: How should heavy construction equipment be loaded, secured, and unloaded on an equipment trailer?
- Load as close to rated capacity as possible, and always position a spotter on the trailer to keep the machine centered on the ramps and trailer. Use low banks or built-up earth ramps when you can; when loading a dozer up trailer ramps, go slowly with the blade raised, slow or stop at the balance point, lower the blade so the front of the tracks settles gently, then ease forward. After positioning, block and chock the equipment and chain it to the trailer, distributing the weight on the marked load-centering positions. Unload slowly, always using ramps. If rear loading is restricted, load from the side without damaging the trailer bed.
- TM 3-34.62 (30 May 2025 incl. C1, 29 Jul 2026), paras 10-13 through 10-18 and figure 10-4
- 12N deep dive: What is optimum moisture content (OMC), and in what range should a 12N usually compact soil?
- Each soil has a specific OMC at which it can reach maximum density for a given amount of compactive energy. Compacting above or below that optimum is very challenging. OMC typically ranges from about 12 to 25 percent for fine-grained soils and from 7 to 12 percent for well-graded granular soils. Because the exact OMC is hard to hit and hold, the usual practice is to work within about ±2 percent of optimum. Determining OMC requires a laboratory test (see also TM 3-34.64). The water-content ratio is the weight of water in the soil divided by the weight of the soil solids.
- TM 3-34.62 (30 May 2025 incl. C1, 29 Jul 2026), para 11-1
- 12N deep dive: In the TM 3-34.62 example, how much water must be added per station for a 6-inch compacted lift?
- 2,017 gallons per station for each lift. The example uses a 40-foot-wide roadway, a target dry unit weight of 120 pounds per cubic foot, an OMC of 12 percent, and borrow material at 5 percent moisture. If the road width stays the same, total water equals gallons per lift times the number of lifts times the road length in stations (100 feet each). Water weighs 8.33 pounds per gallon. It is advisable to aim for OMC plus 2 percent, depending on temperature, wind, and soil type.
- TM 3-34.62 (30 May 2025 incl. C1, 29 Jul 2026), paras 11-4 and 11-5
- 12N deep dive: In that same example, what water application rate is required in gallons per square yard?
- 4.5 gallons per square yard. After the total amount is known, convert it to an application rate so the water can be spread uniformly, regardless of the method used.
- TM 3-34.62 (30 May 2025 incl. C1, 29 Jul 2026), paras 11-6 through 11-8
- 12N deep dive: How does a truck-mounted water distributor apply water to a fill?
- It is the most common method. A typical truck-mounted distributor holds 1,000 gallons and can deliver water under varying pressure or by gravity through a 12-foot folding rear spray bar that is adjustable from 4 to 24 feet in one-foot increments. The operator controls forward speed and distribution pressure to hold the desired rate in gallons per square yard; a cab-mounted odometer shows speed in feet per minute. The project officer gives the operator the required application rate.
- TM 3-34.62 (30 May 2025 incl. C1, 29 Jul 2026), para 11-9 and figure 11-1
- 12N deep dive: What is ponding, and how does weather change water-application planning?
- Ponding means adding water by flooding the area until the desired moisture penetration is reached. The rate is hard to control, and ponding typically takes several days for uniform moisture. Cold, rainy, cloudy, or calm weather helps soil retain or gain moisture; hot, dry, sunny, or windy weather dries it. In desert climates, evaporation can be so great that engineers may add up to 6 percent above the OMC in their water-application calculations so the moisture is close to the desired level when the material is placed and compacted.
- TM 3-34.62 (30 May 2025 incl. C1, 29 Jul 2026), paras 11-10 and 11-11
- 12N deep dive: How can soil that is wetter than the optimum moisture range be dried before compaction?
- Excess moisture makes the desired density hard to reach. Simple drying is aeration; more complex methods include adding a stabilization agent such as lime or fly ash to fine-grained soils, or using subsurface drainage if a high water table is the cause. Scarify the soil before compaction with grader scarifying teeth, a stabilizer mixer, or a disk, or use the grader blade to turn the soil into furrows so more surface area can dry. Mix water or a drying agent thoroughly and evenly; even when no water is added, mixing may still be needed for uniform moisture.
- TM 3-34.62 (30 May 2025 incl. C1, 29 Jul 2026), paras 11-12 and 11-13
- 12N deep dive: How does a stabilizer mixer blend or aerate soil?
- It has a rear-mounted, removable-tine rotating tiller blade under a removable hood that forms an enclosed mixing chamber. The tiller lifts the material, throws it against the hood, and drops it back on the tines for thorough mixing, then ejects it so the trailing edge of the hood leaves a relatively level surface. With the trailing edge fully open, the churned soil has a high void content and dries faster in sun and wind. Models with a spray bar can add water or stabilizing agents during blending. It is designed for material less than 4 inches in diameter, and the tines on the Army mixer can penetrate up to 12 inches below the existing surface.
- TM 3-34.62 (30 May 2025 incl. C1, 29 Jul 2026), para 11-15 and figures 11-2 and 11-3
- 12N deep dive: How does TM 3-34.62 distinguish compaction from consolidation?
- Compaction is mechanically densifying soil, typically by applying a dynamic load. Consolidation is the gradual densification of soil under a static load. Done correctly, compaction also alters the soil’s volume and reduces permeability (the rate at which water flows through the soil). Not all soils respond equally to compaction, but the benefits still make it a crucial part of horizontal construction.
- TM 3-34.62 (30 May 2025 incl. C1, 29 Jul 2026), para 11-16
- 12N deep dive: What four methods does compaction equipment use to densify soil, and what should guide the effort?
- Static weight (pressure), kneading (manipulation), impact (sharp blow), and vibration (shaking). Compactive effort is the energy used to compact a soil mass and should be based on the soil’s physical properties—gradation (well-graded or poorly graded), the Atterberg limits (cohesive or cohesionless), and the required final density.
- TM 3-34.62 (30 May 2025 incl. C1, 29 Jul 2026), para 11-17
- 12N deep dive: In general, which rollers work best on which soils?
- Tamping-foot compactors, which generate high unit pressures, are most effective on predominantly fine-grained cohesive materials such as clays and sandy clays. Large steel-drum rollers are more suitable for larger-particle materials such as gravel or cobble. Vibratory rollers are ideal for well-graded or gap-graded materials because their shaking action helps smaller particles fill voids around larger grains. Also consider the soil type and properties, desired density, lift thickness, size of the job, and the equipment available. Handheld vibratory tampers suit small or confined areas; large self-propelled rollers suit extensive horizontal work.
- TM 3-34.62 (30 May 2025 incl. C1, 29 Jul 2026), paras 11-18 and 11-19
- 12N deep dive: How does a tamping-foot (sheepsfoot-type) roller compact a lift, and what are its limits?
- Square or angular feet taper down away from the drum so they penetrate on the first pass and compact the lift from the bottom to the top, then “walk out” when the desired density is reached. It is suitable for all fine-grained materials but generally not effective on cohesionless granular materials. Maximum compacted lift thickness is 8 inches. Loosen any material already packed by equipment wheels before rolling. It does not effectively compact the upper 2 to 3 inches of a lift, so follow with a pneumatic-tired or smooth-drum roller.
- TM 3-34.62 (30 May 2025 incl. C1, 29 Jul 2026), para 11-20 and figure 11-4
- 12N deep dive: When are pneumatic-tired rollers effective, and what Army models does TM 3-34.62 describe?
- They are effective on most granular materials but unsuitable for fine-grained clays. They use static load and kneading. The Army uses a towed 13-wheel model and a variable-pressure, self-propelled nine-wheel model. The nine-wheel roller can change contact pressure by changing tire pressure and wheel load. The towed 13-wheel model exerts about 210 pounds of contact pressure per inch of rolling width.
- TM 3-34.62 (30 May 2025 incl. C1, 29 Jul 2026), para 11-21 and figures 11-5 and 11-6
- 12N deep dive: What is a dual-drum vibratory roller best used for, and how thick a layer should it compact?
- It can compact a wide range of materials from sand to cobble and is ideal for asphalt paving, cohesionless subgrades, base courses, and wearing surfaces. It is especially effective immediately behind a blade, leaving a smooth, dense, watertight subgrade finish. Because of its relatively low unit pressure and top-down compaction, it is typically used for shallow layers (less than 4 inches). The smooth steel drum is especially suited for finishing base or wearing courses. Avoid excessive crushing of base-course material. It is the preferred roller for asphalt paving.
- TM 3-34.62 (30 May 2025 incl. C1, 29 Jul 2026), para 11-22 and figure 11-10
- 12N deep dive: When is a smooth-drum vibratory roller most effective, and what loose-lift depth is recommended?
- It is particularly effective on noncohesive and nonplastic sands and gravels used in subbase and base courses. Vibration plus the drum’s ballast weight rearranges particles into a dense mass. Because of its relatively light weight, the recommended maximum loose-lift depth (before compaction) is 9 inches. Amplitude is the throw of the vibration and affects how deep it penetrates; frequency is how many oscillations occur in a given time.
- TM 3-34.62 (30 May 2025 incl. C1, 29 Jul 2026), para 11-23 and figure 11-11
- 12N deep dive: What is a jay tamper used for?
- It is a small, self-contained, hand-operated gasoline-powered vibratory compactor, resembling a power lawn mower, used in confined spaces such as trenches around pipes or inside existing structures. It needs no supply lines or auxiliary equipment.
- TM 3-34.62 (30 May 2025 incl. C1, 29 Jul 2026), paras 11-24 and 11-37 and figure 11-12
- 12N deep dive: What should a compaction test strip determine, and how is it run?
- Locate the strip next to the project and use it to find the most effective compactor, optimum lift depth, optimum speed, number of passes, ballast required, and vibration frequency. Start by placing a 6-inch uncompacted lift and running each piece of equipment over a designated length for a set number of passes, typically three, then density-test the sections. After the best roller is identified, use more strips to refine lift thickness, passes, speed, and, for a vibratory roller, resonant frequency.
- TM 3-34.62 (30 May 2025 incl. C1, 29 Jul 2026), paras 11-25 and 11-26
- 12N deep dive: How is compactor production estimated in compacted cubic yards per hour?
- Production = (16.3 × W × S × L × E) ÷ N, where 16.3 converts feet, mph, and inches to CCY; W is compacted width per pass in feet; S is speed in mph; L is compacted lift thickness in inches; E is efficiency; and N is the number of passes required. Use test-strip data for speed, lift, and passes. Daytime efficiency is generally 50 minutes of work per hour; nighttime, 45 minutes. Use the average speed of the individual passes.
- TM 3-34.62 (30 May 2025 incl. C1, 29 Jul 2026), paras 11-27 and 11-28
- 12N deep dive: In the TM 3-34.62 example, how many compactors are needed if 1,500 LCY of blasted rock is delivered per hour?
- Three. The example divides 1,500 LCY per hour times a 0.87 soil conversion factor by 487 CCY per hour of compactor production, getting 2.7, which is rounded up to 3 compactors.
- TM 3-34.62 (30 May 2025 incl. C1, 29 Jul 2026), para 11-29 and table 1-1
- 12N deep dive: What is subgrade, and how is it often prepared with SCIP?
- Subgrade is the in-place soil on which a road, airfield, or heliport is built, to the depth that affects structural design or that climate affects—up to 10 feet for pavements that support heavy loads. Highly organic subgrade may have to be removed and replaced. Heavy pneumatic-tired rollers are preferred because they can compact to depths of up to 18 inches. Often the top 6 inches is scarified to adjust moisture and then recompacted to a higher density than at natural moisture; that process is called scarify and compact in place (SCIP). A tamping-foot roller is effective for SCIP because it loosens and compacts and helps break up oversized material; finish the top 1 to 2 inches, or seal the surface if rain is expected, with a pneumatic-tired or smooth-drum roller. If a lift is already sealed, scarify the top 1 to 2 inches before the next lift so the layers bond. For sand, a vibratory compactor is most effective.
- TM 3-34.62 (30 May 2025 incl. C1, 29 Jul 2026), paras 11-30 through 11-33
- 12N deep dive: How thick should uncompacted fill lifts be, and from which direction should fill be spread?
- Typically the uncompacted lift is 1.5 to 2 times the final compacted thickness—for example, place fill in 9- to 12-inch layers to get a 6-inch compacted lift. Spread the material in uniform layers with a relatively even surface, using a scraper or dump truck and a dozer or grader. Spreading from the farthest point toward the source lets hauling equipment further compact the subgrade and reveals undetected weaknesses. Spreading from the nearest point toward the farthest lets haul equipment travel over the newly spread material, which compacts it and significantly reduces the later compaction effort.
- TM 3-34.62 (30 May 2025 incl. C1, 29 Jul 2026), paras 11-34 and 11-35
- 12N deep dive: What roller operating rules cover overlap, turning, and aerating?
- Each pass should overlap the preceding pass by at least 1 foot so no uncompacted strips are left. Make gradual turns at the end of each pass to avoid damaging the lift surface or a towed roller’s tongue. When using the roller to aerate soils, travel at the highest practical speed so the material is kicked up rather than densified.
- TM 3-34.62 (30 May 2025 incl. C1, 29 Jul 2026), paras 11-38 through 11-40
- 12N deep dive: What is a single surface treatment versus a multiple surface treatment?
- A single surface treatment is a sprayed bituminous material followed by a one-stone-thick aggregate cover; it serves as both a wearing surface and waterproofing and takes minimal equipment, materials, and time. Repeating that process produces a multiple surface treatment, which is denser for wear and waterproofing and also adds structural integrity. Adding later treatments or thicker pavement when time and materials allow is called stage construction.
- TM 3-34.62 (30 May 2025 incl. C1, 29 Jul 2026), paras 12-1 and 12-2
- 12N deep dive: What must a sweeper and an asphalt distributor be checked for before surfacing work?
- A sweeper removes dust so new asphalt can bond to the base or old pavement; inspect it for excessive bristle wear and a working power drive on all brooms. A dust layer on a base course can also be removed by wetting the base and recompacting it. The Army asphalt distributor is a truck-mounted 1,500-gallon insulated tank with a low-pressure heating system, a rear hydraulic pump, and an adjustable spray bar. Keep the heater and pump maintained; keep gauges, the pump tachometer, measuring stick, thermometers, and bitumeter calibrated; and keep spray bars and nozzles clean and at the correct height.
- TM 3-34.62 (30 May 2025 incl. C1, 29 Jul 2026), paras 12-3 and 12-4 and figure 12-1
- 12N deep dive: What heating and spraying safety rules apply to an Army asphalt distributor?
- The two diesel burners fire into U-shaped fire tubes at the bottom of the tank. Keep at least 3 inches of asphalt covering those tubes to prevent overheating, fire, or explosion. Heat only in a well-ventilated area, with the truck leveled and completely stopped. Application rate is controlled by spray-bar length, bitumen-pump output (shown in gallons per minute on the cab tachometer), and the truck’s forward speed (shown in feet per minute on the bitumeter).
- TM 3-34.62 (30 May 2025 incl. C1, 29 Jul 2026), paras 12-5 and 12-6 (including the warning)
- 12N deep dive: What general construction-equipment safety rules does TM 3-34.62 chapter 13 list?
- Inspect equipment before use and regularly thereafter. Use seat belts when they are available. Provide barriers so no one walks under hoist- or lift-capable loading equipment. Observe safe speeds and do not endanger persons or property. Shut down and turn off the engine when the equipment is unattended, and also when refueling. Stop completely and apply the parking brake, if available, before mounting or dismounting. Do not operate any machinery more than 10 consecutive hours without an 8-hour rest interval. Post safe load capacities at the operator’s position on equipment not rigged to prevent overloading, and post safe operating speeds on equipment that has no speed governor. Mount a ROPS whenever it is available, and do not modify it. Ensure that only the operator is on the equipment while it is running, except when a supervisor authorizes an exception for an emergency, some training, or required maintenance.
- TM 3-34.62 (30 May 2025 incl. C1, 29 Jul 2026), para 13-2
- 12N deep dive: What lock-out and blocking rules apply when construction equipment is being repaired?
- Besides the unit SOP, shut down or lock out the controls while a machine is repaired, adjusted, or serviced, and move it to a safe place away from the project for the mechanic to work. Crib or block suspended machinery, parts, and machines held apart by slings, hoists, or jacks; do not work underneath or between items that are not properly blocked. Lower blades, bowls, hooks, buckets, and forks to the ground or onto suitable blocking during maintenance.
- TM 3-34.62 (30 May 2025 incl. C1, 29 Jul 2026), para 13-6
- 12N deep dive: When must a wire rope or cable be removed from hoisting service?
- If it is kinked or has multiple broken wires in any strand, and specifically when three broken wires are found in one strand of 6×7 rope, six in one strand of 6×19, eight in one strand of 8×19, or nine in one strand of 6×37. Inspect during installation and as part of daily operator maintenance. Plainly mark defective rope as unsuitable and dispose of it properly. Wear leather gloves when handling wire rope, and use rope only within the manufacturer’s recommended limits.
- TM 3-34.62 (30 May 2025 incl. C1, 29 Jul 2026), paras 13-9 and 13-10
- 12N deep dive: How must a wire-rope eye splice be clipped, and who may attach slings?
- Only qualified rigging personnel should attach slings. Inspect slings daily and replace defective ones. Make eye splices with the proper size of wire-rope thimble. Place the U-bolt of U-bolt clips on the dead (short) end of the rope, and tighten the clips after the first load and at frequent intervals thereafter. The minimum number of clips is three (see table 13-4 for number, spacing, and torque; do not over-torque).
- TM 3-34.62 (30 May 2025 incl. C1, 29 Jul 2026), para 13-11, figure 13-1, and table 13-4
- 12N deep dive: What hook, shackle, and wedge-socket rules apply when rigging loads?
- Replace bent, twisted, damaged, or excessively worn hooks, shackles, rings, pad eyes, and other fittings. Close all hooks used to support human loads or loads that pass over workers, and do not use open hooks where the load or hook might catch or foul and relieve cable tension. For a wedge-socket fastener, extend the dead end of the wire rope six to nine times the rope diameter beyond the socket, clamp that dead end to an extra short piece of wire (never to the live end), place the clamp close to the wedge, and have the U-bolt bear against the tail.
- TM 3-34.62 (30 May 2025 incl. C1, 29 Jul 2026), para 13-12 and figure 13-2
- 12N deep dive: What must happen when a truck is loaded by a suspended or overhead device, and how should oversize equipment be moved?
- The operator of the truck being loaded must leave the cab. When loading equipment for transport, distribute, chock, and tie down the load; keep forward and side vision clear; and keep the load within the sides of the hauling equipment, with adequate warnings if it is oversize. For equipment wider than a standard vehicle or that protrudes past the trailer, travel or transport in daylight, use warning flags and/or lights, and accompany it with a lead and/or follow vehicle with warning signs whenever possible, especially in congested or heavy traffic.
- TM 3-34.62 (30 May 2025 incl. C1, 29 Jul 2026), paras 13-13 and 13-14
- 12N deep dive: What night-operation and excavation-protection rules does TM 3-34.62 give?
- At night, equip all mobile equipment with adequate headlights and taillights, keep construction roads and working areas well illuminated until all workers have left, and have signalers, spotters, inspectors, and maintenance personnel who work in the dark near traffic wear reflectorized vests if the tactical situation permits. When excavating, shore, brace, or slope excavations more than 4 feet deep unless the material is solid rock, hard shale, hardpan, cemented sand and gravel, or similar material (the TM rule; OSHA 29 CFR 1926.652 sets its protective-system threshold at 5 feet, so follow whichever rule is stricter). Design shoring and bracing to be effective all the way to the bottom, and add protection when excavating next to backfill or where traffic or machinery vibration may cause slides.
- TM 3-34.62 (30 May 2025 incl. C1, 29 Jul 2026), paras 13-15 and 13-16
- 12N deep dive: How does the Unified Soil Classification System (USCS) group soils, and what letter symbols does it use?
- The USCS is based on the characteristics that show how a soil will behave as a construction material. All soils are placed in one of three major categories: coarse-grained, fine-grained, or highly organic. Letter symbols include S for sand, G for gravel, M for silt, and C for clay. A sandy clay is designated SC. Borderline soils may need a dual symbol, such as SM-SC for a sand that contains appreciable silt and clay.
- TM 3-34.64 (25 Sep 2012), paras 5-1 through 5-4
- 12N deep dive: How does USCS decide whether a soil is coarse-grained, and how are gravels and sands subdivided?
- Coarse-grained soils are those in which at least half the material is retained on a Number 200 sieve. They are divided into gravels and sands. The soil is classed as gravel (G) if more than half the coarse fraction by weight is retained on a Number 4 sieve; otherwise it is sand (S). Gravels are further separated into coarse or fine at the ¾-inch sieve, and sands into coarse, medium, or fine at the Number 10 and Number 40 sieves. Where a mixture occurs, the predominant fraction is the primary name (for example, a sandy gravel contains more gravel than sand).
- TM 3-34.64 (25 Sep 2012), paras 5-5 and 5-6
- 12N deep dive: How are coarse-grained soils with less than 5 percent fines classified under USCS?
- They may be GW (well-graded gravels and gravel-sand mixtures with little or no fines), SW (well-graded sands and gravelly sands with little or no fines), GP (poorly graded gravels and sandy gravel mixtures with little or no fines), or SP (poorly graded sands and gravelly sands with little or no fines). For GW, the coefficient of uniformity (Cu) must be greater than 4; for SW, greater than 6. For both well-graded groups, the coefficient of curvature (Cc) must be between 1 and 3. The fines must not notably change the strength or free-draining characteristics of the coarse fraction. GP and SP do not meet those gradation requirements.
- TM 3-34.64 (25 Sep 2012), para 5-7
- 12N deep dive: How are coarse-grained soils with more than 12 percent fines classified, and when are dual symbols required?
- They may be GM (silty gravel) or SM (silty sand) if the Atterberg limits plot below the A-line of the plasticity chart, or GC (clayey gravel) or SC (clayey sand) if the limits plot above the A-line. Gradation is not considered significant for these groups. M versus C is based on the plasticity of the material passing the Number 40 sieve, using the liquid limit and plasticity index. Coarse-grained soils with 5 to 12 percent passing the Number 200 sieve that also meet well-graded criteria get dual symbols such as GW-GM, GW-GC, SW-SM, or SW-SC. Soils with more than 12 percent fines whose limits plot in the hatched (borderline) portion of the plasticity chart are classified SM-SC or GM-GC. If more than one borderline zone applies, use only a double symbol and, if in doubt, the poorer grouping.
- TM 3-34.64 (25 Sep 2012), paras 5-8 through 5-14 and figure 5-1
- 12N deep dive: How are fine-grained soils classified under USCS?
- Fine-grained soils are those in which more than half the material passes a Number 200 sieve. They are classified by plasticity and compressibility, not grain size, using the relationship between liquid limit and plasticity index on the plasticity chart. L groups have liquid limits less than 50 (low compressibility); H groups have liquid limits of 50 or more (high compressibility). They are further divided by whether they plot above or below the A-line.
- TM 3-34.64 (25 Sep 2012), paras 5-15 and 5-16
- 12N deep dive: What do the fine-grained USCS group symbols ML, MH, CL, CH, OL, and OH represent?
- ML and MH are inorganic silts that plot below the A-line; ML is low plasticity and includes very fine sands, rock flours, and slightly plastic silty or clayey fine sands, while MH includes micaceous and diatomaceous soils and plastic silts. CL and CH are inorganic clays that plot above the A-line; CL includes gravelly, sandy, silty, and lean clays, and CH includes fat clays, gumbo clays, volcanic clays, and bentonite. OL and OH are characterized by organic matter and generally plot below the A-line: OL is organic silts and organic silt-clays of low plasticity, and OH is organic clays. Fine-grained soils whose limits plot in the shaded portion of the chart get dual symbols such as CL-ML.
- TM 3-34.64 (25 Sep 2012), paras 5-17 through 5-21
- 12N deep dive: How is highly organic soil (Pt) identified, and which laboratory tests are used to classify other soils?
- A special classification, Pt, is reserved for highly organic soils such as peat. There are no laboratory criteria; they are generally identified in the field by distinctive color and odor, a spongy feel, and often a fibrous texture, frequently with particles of leaves, grass, branches, or other vegetable matter. For other soils, the principal laboratory tests are mechanical analysis, liquid limit, and plastic limit. With the percentages of gravel, sand, and fines plus the liquid limit and plasticity index, the group symbol is obtained from table 5-2. For gravels and sands with 5 percent or less fines, the shape of the grain-size curve shows whether the material is well-graded or poorly graded.
- TM 3-34.64 (25 Sep 2012), paras 5-22, 5-25, and 5-26 and table 5-2
- 12N deep dive: What properties are desired in soils used as foundations under roads and airfields?
- Adequate strength, resistance to frost action (where frost is a factor), acceptable compression and expansion, adequate drainage, and good compaction. Low subgrade strengths may be compensated for in many cases by increasing the thickness of overlying base materials or using a geotextile. Strength requirements for base-course materials are high, and only good-quality materials are acceptable. If freely draining materials are not available locally, adequate drainage may be obtained by installing a properly designed water-collecting system.
- TM 3-34.64 (25 Sep 2012), paras 5-27 and 5-28
- 12N deep dive: Which soil properties does compaction change, and why is it used in embankments and pavements?
- Compaction, when properly controlled, produces a marked change in settlement, shearing resistance, movement of water, and volume change at relatively low cost. It is a standard procedure in building embankments, subgrades, and bases for road and airfield pavements. It does not improve all soils to the same degree; for some soils, holding volume change to a minimum may be more important than just increasing shearing resistance.
- TM 3-34.64 (25 Sep 2012), paras 8-1 and 8-2
- 12N deep dive: How does compaction reduce settlement and increase shearing resistance in an embankment?
- Compaction and consolidation both bring soil particles closer together, so densification by compaction prevents later consolidation and settlement within the body of the embankment. The embankment may still settle if its weight consolidates compressible layers in the foundation. Increasing density usually increases shearing resistance, which may allow a thinner pavement over a compacted subgrade or steeper embankment side slopes. For the same density, the highest strengths are frequently obtained with greater compactive effort at water contents somewhat below optimum moisture content.
- TM 3-34.64 (25 Sep 2012), paras 8-3 through 8-5
- 12N deep dive: How does compaction affect water movement and volume change, especially in clay subgrades?
- Forcing particles together reduces the number and size of voids, which reduces permeability and seepage. With proper moisture control, capillary water movement is also minimized, so the soil is less likely to take up water and later lose shearing resistance. Volume change (shrinkage and swelling) is critical in subgrades for roads and airfields and is a particular concern with clays: the greater the density, the greater the potential swell unless the soil is restrained. An expansive clay should be compacted at a moisture content at which swelling will not exceed 3 percent. The effect of swelling on bearing capacity is evaluated in the standard Corps of Engineers method of preparing samples for the CBR test.
- TM 3-34.64 (25 Sep 2012), paras 8-6 and 8-7
- 12N deep dive: What is the moisture-density relationship, and what is optimum moisture content?
- Nearly all soils, under a given compactive effort, develop a maximum dry density at an optimum moisture content (OMC). OMC is the moisture at which the soil becomes sufficiently workable that most of the air is expelled and the particles pack closely. For most soils except cohesionless sands, the soil is more difficult to compact drier than optimum; wetter than optimum, water interferes with close packing so density drops. Beyond optimum the air content of most soils stays essentially the same even if more water is added. That moisture-density curve is valid in both the laboratory and the field, and the maximum dry density is often treated as 100 percent compaction for that soil and that effort.
- TM 3-34.64 (25 Sep 2012), paras 8-8 and 8-9 and figure 8-1
- 12N deep dive: What is the Corps of Engineers CE 55 compaction test, and how does it compare with Proctor tests?
- CE 55 is the standardized laboratory compactive effort adopted by the U.S. Army Corps of Engineers (MIL-STD-631A). Table 8-1 lists CE 55 as 55 blows per layer, 5 layers, a 10-pound hammer, an 18-inch drop, and a 6-inch mold of 0.07636 cubic feet. CE 12 uses the same mold and hammer but only 12 blows per layer. ASTM D-1557 (modified Proctor) and AASHTO T-180 are the civilian modified counterparts; ASTM Standard Proctor and AASHTO T-99 use a 5.5-pound hammer, a 12-inch drop, and 25 blows on 3 layers in a 4-inch mold. The names of these tests are often used interchangeably in publications.
- TM 3-34.64 (25 Sep 2012), para 8-10 and table 8-1
- 12N deep dive: What is the zero air-voids curve on a moisture-density plot?
- It is obtained by plotting the dry densities that would correspond to complete saturation at different moisture contents, and it represents theoretical maximum densities for given water contents. Those densities are practically unattainable because compaction alone cannot remove all the air in the voids. Typically, beyond optimum moisture, the actual compaction curve closely parallels the zero air-voids curve. Any dry-density value that plots to the right of the zero air-voids curve is in error.
- TM 3-34.64 (25 Sep 2012), para 8-11 and figure 8-1
- 12N deep dive: How do typical CE 55 maximum dry densities and optimum moisture contents vary among soils?
- Extremely light soils such as diatomaceous earths and some volcanic soils may have maximum densities as low as 60 pounds per cubic foot under a given effort; a clay may be in the range of 90 to 100 pcf, and a well-graded coarse granular soil may be as high as 135 pcf. Optimum moisture typically varies from about 12 to 25 percent for fine-grained soils and from 7 to 12 percent for well-graded granular soils. For some clay soils, OMC and the plastic limit will be approximately the same. Heavy clays can be compacted over a relatively wide range of moisture below optimum with comparatively small density change, but if they are compacted more than about 2 percent wetter than OMC they become nearly unworkable. Well-graded granular soils react sharply to slight moisture changes.
- TM 3-34.64 (25 Sep 2012), paras 8-12 through 8-14 and figure 8-2
- 12N deep dive: How should water be added to, or removed from, soils that are being compacted?
- Water can be added in the borrow pit or in place and must be thoroughly and uniformly mixed with the soil; mixing may still be desirable even if no water is needed, to ensure uniformity. Sprinkling and mixing in place generally give the best results for granular materials. Mixing can be done with motor graders, rotary mixers, and commercial harrows to a depth of 8 inches or more. If time allows, the pit may be diked or ponded and flooded until the desired penetration is reached, which usually takes several days. Medium clayey soils work best with sprinkling and cultivators or rotary mixers, in lifts up to 8 inches or more. Heavy clay soils present many difficulties and should never be used as fill in an embankment foundation; they should be left undisturbed. When soils are too wet, dry them by manipulating and exposing them to air and sun with cultivators, plows, graders, or a rotary mixer with the tail hood raised, or mix wet and dry soils together. In hot weather, handle the soil quickly so evaporation does not force extra watering and mixing.
- TM 3-34.64 (25 Sep 2012), paras 8-16 through 8-19
- 12N deep dive: What happens to optimum moisture and maximum density when compactive effort is increased, and what controls effort in the field?
- If the compactive effort is increased, the maximum density increases and the optimum moisture content decreases. The relationship is not linear: it takes a considerably greater increase in effort to raise a clay from 90 to 95 percent of CE 55 maximum density than to make the same change in a sand. In the field, compactive effort is a function of the roller’s weight and the number of passes for the width and depth being rolled. Increasing weight or passes generally increases effort. Other factors include lift thickness, contact pressure, the size and length of tamping feet on a sheepsfoot roller, and the frequency and amplitude of a vibratory compactor.
- TM 3-34.64 (25 Sep 2012), paras 8-20 and 8-21 and figure 8-3
- 12N deep dive: What is a specifications block on a CE 55 compaction curve, and what minimum compaction does table 8-2 require?
- Strength can decrease with increased compaction, particularly in cohesive materials, so a “window” is normally set as a 5 percent range for density and a 4 percent range for moisture and plotted on the CE 55 curve; that window is the specifications block. Figure 8-4 shows an example of 90 to 95 percent compaction and 12 to 16 percent moisture. Table 8-2 minimums include 100 percent compaction for cohesionless base (CBR greater than 80) and cohesionless subbase (CBR 20 to 50); for select subgrade with CBR less than 20, 95 percent if cohesionless and 90 percent if cohesive (or 100 percent if subgrade CBR is greater than 20); in traffic areas and embankment fill, 95 percent cohesionless and 90 percent cohesive; and in nontraffic areas, 90 percent cohesionless and 85 percent cohesive.
- TM 3-34.64 (25 Sep 2012), para 8-23, table 8-2, and figure 8-4
- 12N deep dive: In the CBR compaction-design method, how are free-draining, swelling, and nonswelling soils recognized?
- Start with the CE 55 compaction curve on DD Form 2463, page 1. If the curve is U-shaped, the soil is classified as free-draining for CBR analysis. If it is bell-shaped, use the swell data on DD Form 1211. Soils that, when saturated, increase in volume more than 3 percent at any initial moisture content are classified as swelling soils. Regardless of class, the density value from the peak of the CE 55 moisture-density curve is the maximum dry density (γdmax).
- TM 3-34.64 (25 Sep 2012), paras 8-24 and 8-25 and figure 8-5
- 12N deep dive: What design moisture and density ranges does the CBR method assign to free-draining, swelling, and nonswelling soils?
- For nonswelling soils, OMC is used and the design moisture-content range is +2 percent. For swelling and free-draining soils, minimum moisture content (MMC) is used, and the design moisture-content range is MMC + 4 percent. For swelling soils, MMC is the moisture at which 3 percent swell occurs. For free-draining soils, MMC is the moisture that corresponds to γdmax (the point after which more water does not increase density). Free-draining soils are compacted to 100 to 105 percent of γdmax, and swelling soils to 90 to 95 percent of γdmax. For nonswelling soils, if the plasticity index is greater than 5 the soil is cohesive and is compacted to 90 to 95 percent of γdmax; if CBR values are consistently above 20, compact to 100 to 105 percent of γdmax; otherwise compact to 95 to 100 percent of γdmax.
- TM 3-34.64 (25 Sep 2012), paras 8-25 through 8-27
- 12N deep dive: How close to optimum moisture should plastic and cohesionless subgrades be compacted, and how are cut-section subgrades treated in the theater of operations?
- Plastic soils should be compacted at moisture contents close to optimum. They generally cannot be compacted satisfactorily more than 10 percent above or below optimum, and much better results are obtained if moisture is held to within 2 percent of optimum. Moisture control is less critical for cohesionless soils, but some sands bulk at low moisture and should not be compacted until that is corrected; they are normally compacted at moisture contents approaching 100 percent saturation. In theater-of-operations cut sections, subgrade soil should be scarified to a depth of about 6 inches and recompacted (a SCIP operation) for uniformity. In fill, the subgrade is the top layer of the embankment, compacted to the required density and brought to grade and section.
- TM 3-34.64 (25 Sep 2012), paras 8-30 and 8-31
- 12N deep dive: How should expansive clays, remolding-sensitive clays, and pumping silts be handled as subgrades?
- Soils with a high clay content, particularly CH, MH, and OH, may expand detrimentally if compacted to a high density at low moisture and then exposed to water. If they must be used, compact them to the maximum density obtainable at the minimum moisture content that keeps swelling to a minimum; swelling soils placed drier than that MMC can be expected to swell more than 3 percent, and volume increases up to 3 percent generally do not adversely affect theater-of-operations structures. Certain CH and OH soils lose strength when remolded, even if compacted to design density in a cut, and should be removed from the site. Some silts and very fine sands (predominantly ML and SC) can pump water and become “quick” when compacted over a high water table, losing shearing strength; lower the water table, dry them, or remove and replace localized areas. If they cannot be dried or removed, leave them undisturbed and add cover so the subgrade is not overstressed.
- TM 3-34.64 (25 Sep 2012), paras 8-32 through 8-34
- 12N deep dive: How thick should compacted base layers be, and what can later change a compacted soil’s density?
- Selected soils used in base construction must be compacted to the general requirements, and the thickness of layers must stay within limits that ensure proper compaction—generally 4 to 8 inches, depending on the material and method of construction. Frost action may later change the density of a compacted soil, particularly if it is fine-grained. Heavy traffic, especially on airfield subgrades and bases, may increase density after construction and cause rutting of a flexible pavement or subsidence of a rigid pavement. Good shoulders, tight joints in a concrete pavement, and adequate drainage help maintain the compaction achieved during construction.
- TM 3-34.64 (25 Sep 2012), paras 8-36 and 8-40
- 12N deep dive: What is soil compressibility, and how does settlement of cohesionless soil differ from consolidation of clay?
- Compressibility is the property that lets a soil deform under an external compressive load, such as the weight of a highway or airfield. The reduction in volume comes from a reduction in void space, not from crushing the particles or the water in the voids. If the soil is saturated, water must be forced from the voids before settlement can take place; that process is called consolidation, and its rate depends on how quickly water can escape (permeability). The compressibility of confined coarse-grained cohesionless soils is rarely a practical concern: settlement is usually small and occurs rapidly during loading, and deformations are essentially permanent, with little rebound when the load is removed. Loose sand is much more compressible than dense sand and should be avoided or compacted before loading. Clay consolidation under a comparable load may be much greater and may take a very long time; uniform settlement may not be critical, but differential settlement can seriously damage a structure or a pavement on an embankment.
- TM 3-34.64 (25 Sep 2012), paras 6-3 through 6-10
- 12N deep dive: Why is shearing resistance important, and how is CBR used to measure it for military construction?
- Shearing resistance (shear strength) is related to a soil’s ability to withstand loads, including the bearing capacity of a base or subgrade under a road, runway, or other structure, the stability of cut or embankment slopes, and the pressures against a retaining wall. Laboratory shear tests include the direct shear, triaxial compression, and unconfined compression tests, but military soils analysts are not equipped or trained to perform the direct shear or triaxial tests. For most military applications, the California Bearing Ratio (CBR) is used as a measure of shear strength. CBR is a measure of shearing resistance under carefully controlled density and moisture conditions, determined by a penetration shear test and used with empirical curves to design flexible pavements. The design CBR procedure is to prepare specimens, perform the penetration test, and perform a swell test. Specimens are compacted to duplicate field conditions as nearly as possible—nearly dry in a desert, or at about 100 percent saturation in a wet area. Tests may also be run on undisturbed samples or in-place in the field.
- TM 3-34.64 (25 Sep 2012), paras 6-13 through 6-19
- 12N deep dive: What typical field CBR values does TM 3-34.64 associate with USCS soil groups?
- Column 15 of table 5-3 shows typical field CBR ranges. Values may be as low as 3 for highly plastic inorganic clays (CH) and some organic clays and silts (OH), and as high as 80 for well-graded gravel and gravel-sand mixtures.
- TM 3-34.64 (25 Sep 2012), para 6-20 and table 5-3, column 15
- 12N deep dive: What is the airfield cone penetrometer, and how does it differ from the trafficability penetrometer?
- The airfield cone penetrometer is a compact, sturdy probe used to determine an Airfield Index (AI) of soil strength. It has a right circular cone with a ½-inch base diameter on a graduated staff, with a spring, load indicator, and handle at the other end; assembled length is 36 1/8 inches, and it can be broken into three pieces for carrying. Its range is 0 to 15. It must not be confused with the trafficability penetrometer in the Soil Test Set, which has a dial load indicator (0 to 300) and two cones (½ inch, 0.2 square inch, and 0.8 inch, 0.5 square inch). If the trafficability penetrometer is used to measure AI, divide readings from the 0.2-square-inch cone by 20 and readings from the 0.5-square-inch cone by 50.
- TM 3-34.64 (25 Sep 2012), paras 6-21 through 6-25
- 12N deep dive: How is the airfield cone penetrometer operated?
- Check that all joints are tight and that the load indicator reads zero. Place both palms symmetrically on the handle, steady your arms against your thighs, and apply force until a slow, steady downward movement occurs. Read the load indicator when the base of the cone enters the ground (the surface reading) and at desired depths when the corresponding staff mark reaches the soil surface, shifting your line of vision from the surface to the indicator just before the desired depth is reached. A two-person team is most efficient—one operates and reads, the other records. Calibration should be checked occasionally and the instrument recalibrated if the error exceeds about 5 percent.
- TM 3-34.64 (25 Sep 2012), paras 6-26 and 6-27
- 12N deep dive: What METT-T factors should be assessed before deciding to stabilize soil in the theater of operations?
- Mission: what type of facility is being built (road, airfield, or building foundation) and how long it will be used. Enemy: whether the enemy is interdicting lines of communication and how that would affect hauling stabilizing admixtures to the site. Terrain: effects during construction and over the facility’s design life, including erosion and slope stability. Troops and equipment: whether the equipment needed for the work is on hand or can be obtained. Time available: whether the tactical situation allows time to stabilize the soil and, if necessary, let it cure.
- TM 3-34.64 (25 Sep 2012), para 9-1
- 12N deep dive: What are the two broad methods of soil stabilization, and when should each be considered?
- Mechanical stabilization and chemical admixture stabilization; some techniques combine the two. Mechanical methods alter the physical composition of the soil (soil blending) or place a barrier in or on the soil (such as sod to prevent dust). Chemical methods use an admixture to alter the soil’s chemical properties (such as lime to reduce plasticity). Classify the soil by USCS, or by field identification if a soil-testing kit is unavailable. Mechanical stabilization through soil blending is the most economical and expedient way to alter the existing material. Consider geotextiles or chemical admixtures when blending is not feasible or does not produce a satisfactory material, and then determine which admixtures, special equipment, and training are available.
- TM 3-34.64 (25 Sep 2012), paras 9-2 through 9-4
- 12N deep dive: What three essentials are required for a properly mechanically stabilized soil mixture?
- Proper gradation, a satisfactory binder soil, and proper control of the mixture content. Mechanical stabilization produces an interlocking of soil-aggregate particles by compaction; the grading must produce a dense mass when compacted. That can be done by uniformly mixing the material and compacting it, or by blending in additional fines or aggregates first. Uniform mixing and blending are essential for uniform bearing capacity, and the mixture is normally compacted at or near optimum moisture content.
- TM 3-34.64 (25 Sep 2012), paras 9-5 through 9-7
- 12N deep dive: What roles do the coarse and fine fractions play in a mechanically stabilized soil mixture?
- The portion retained on a Number 200 sieve contributes internal friction. Practically any granular material that does not soften when wet or pulverize under traffic can be used, but the best aggregates are hard, durable, and angular, and well-graded from coarse to fine because they are more stable and easier to compact. Satisfactory materials include crushed stone, crushed and uncrushed gravel, sand, and crushed slag; local materials such as disintegrated granite, caliche, coral, limerock, shell, and cinders have also been used. If blended local materials are finer or coarser than specified, satisfy the size requirements of the finer fractions and neglect the gradation of the coarser sizes. The portion that passes a Number 200 sieve acts as filler and supplies cohesion, which helps retain stability in dry weather; swelling of clay can also retard moisture penetration in wet weather. Binders are commonly clay or dust from rock-crushing. Too much fines causes unacceptable volume change, so plasticity is controlled by liquid limit and plasticity index on the material passing the Number 40 sieve, and the amount of fines is limited by the percent passing the Number 200 sieve. Frost action must be considered when designing the mixture.
- TM 3-34.64 (25 Sep 2012), paras 9-8 through 9-10
- 12N deep dive: How can mechanical stabilization be used to fix loose sand or clay subgrades?
- It may be used to prepare soils as subgrades, bases, or surfaces. If the surface is loose sand that cannot support wheeled vehicles, especially when dry, a suitable binder soil can be mixed in the proper proportions to provide an expedient all-weather surface for light traffic (a sand-clay road) or a working platform during construction. Where natural gravels are not available, crushed stone, slag, or similar materials can be stabilized with clay binder to produce a base or surface. A common way to stabilize an existing clay is to add gravel, sand, or other granular material to increase drainability and stability, reduce volume changes, and control the undesirable effects of clays. Under emergency conditions, mixtures of local materials such as shell, coral, soft limestone, cinders, or marl may still give satisfactory service even if they do not meet stated requirements.
- TM 3-34.64 (25 Sep 2012), paras 9-11, 9-12, and 9-21
- 12N deep dive: How can water weaken an unsurfaced road or airfield, and what is the purpose of a soil-surface waterproofer?
- An unsurfaced facility may have the required strength when first built, but water can cause a loss of strength under traffic. Fine-grained soils and granular materials with too many fines are generally more sensitive to water than coarse-grained soils. Surface water can also loosen material that later becomes dust. Water may enter by percolation of rain or ponded surface water, capillary action from groundwater, a rise in the water table, or condensation under a vapor-impermeable surface. A shallow groundwater table generally means low bearing strength and should be avoided. Surface-water problems can usually be lessened by proper grading, compaction, and drainage. A soil-surface waterproofer protects the soil against water and preserves its in-place or as-constructed strength during wet-weather operations; use is generally limited to traffic areas, though waterproofers may also keep shoulders or overruns from softening excessively.
- TM 3-34.64 (25 Sep 2012), paras 9-34 through 9-36
- 12N deep dive: When are chemical admixtures used to stabilize soil, and which four are used most often?
- They are often used when mechanical methods are inadequate and replacing an undesirable soil is not possible or is too costly. Over 90 percent of all chemical-admixture stabilization projects use cement, lime, fly ash, or bituminous materials. Other admixtures exist but are not discussed because they are unlikely to be available in the theater of operations. Chemical admixtures may contain hazardous materials; consult appendix C for the necessary safety precautions. When selecting an additive, consider the type of soil, the purpose of the stabilized layer, the quality improvement desired, the required strength and durability, and cost and environmental conditions.
- TM 3-34.64 (25 Sep 2012), paras 9-38 through 9-40 (including the warning)
- 12N deep dive: What soil and temperature limits apply when using portland cement as a stabilizer?
- Cement can stabilize a wide range of materials, but in general the soil should have a plasticity index less than 30, and for coarse-grained soils more than 45 percent should pass the Number 4 sieve. If the soil temperature is less than 40 degrees Fahrenheit and is not expected to increase for one month, chemical reactions will not occur rapidly and strength gain will be minimal; the cement may then act only as a modifier, and another stabilizer might be considered. Schedule soil-cement work so the mixture gains enough durability to resist expected freeze-thaw cycles. Cement can either modify and improve the soil or transform it into a cemented mass. When a cement-treated base course for Air Force pavements is to be surfaced with asphaltic concrete, the percent of cement by weight is limited to 4 percent.
- TM 3-34.64 (25 Sep 2012), paras 9-44 through 9-46
- 12N deep dive: Which soils react well with lime, and what curing and temperature rules apply?
- Lime reacts with medium-, moderately fine-, and fine-grained soils to decrease plasticity, increase workability and strength, and reduce swell. USCS groups that should be considered potentially capable of being lime-stabilized include CH, CL, MH, ML, SC, SM, GC, GM, and the related dual-symbol groups listed in paragraph 9-53. If the soil temperature is less than 60 degrees Fahrenheit and is not expected to increase for one month, reactions will be slow and strength gain minimal. Lime gains strength slowly and needs about 14 days in hot weather and 28 days in cool weather to gain significant strength; pavement damage can be expected if heavy vehicles use the lime-stabilized soil before a 10- to 14-day curing period. Unsurfaced lime-stabilized soils abrade rapidly under traffic, so a bituminous surface treatment is recommended. Either hydrated lime or quicklime may be used, but most work uses hydrated lime because quicklime is highly caustic and dangerous. Design contents in the TM are for hydrated lime; as a guide, reduce them by 25 percent to get a design content for quicklime.
- TM 3-34.64 (25 Sep 2012), paras 9-53 through 9-56
- 12N deep dive: How is an initial design lime content determined using pH?
- Most lime has a pH of about 12.4 in water, so pH is a good indicator of the desirable lime content. The preferred method is to prepare several mixtures at different lime-treatment levels and measure the pH of each after one hour; the lowest lime content that produces the highest pH is the initial design lime content. The early lime-soil reactions are nearly complete within one hour, although substantial strength gain is not reflected for some time. Changes in the plastic limit and liquid limit are also indicators of the desired lime content. In frost areas, specimens must also be subjected to the freeze-thaw test.
- TM 3-34.64 (25 Sep 2012), para 9-59
- 12N deep dive: How do Class C and Class F fly ash differ as soil stabilizers?
- Fly ash is a pozzolanic by-product of coal-fired electric power plants, consisting mainly of silicon and aluminum compounds that, when mixed with lime and water, can form a hardened cementitious mass. Class C has a high calcium-oxide (CaO) content of 12 percent or more and comes from subbituminous and lignite (soft) coal; lignite fly ash often exceeds 30 percent CaO and can be used as a stand-alone stabilizer, while Class C with less than 25 percent CaO can be improved by adding lime. Class F has a low CaO content (less than 10 percent) and comes from anthracite and bituminous coal; it is not effective by itself, but becomes an effective stabilizer when mixed with lime or with lime and cement.
- TM 3-34.64 (25 Sep 2012), paras 9-61 through 9-63
- 12N deep dive: What initial lime-cement-fly ash (LCF) mix is used for expedient construction?
- Use 1 percent portland cement, 4 percent lime, 16 percent fly ash, and 79 percent soil. Minimum unconfined strength requirements in table 9-4 must be met; if test specimens fall short, add cement in 1/2 percent increments until strength is adequate. In frost-susceptible areas, durability requirements in table 9-5 must also be satisfied. As with cement-stabilized bases, LCF mixtures containing more than 4 percent cement cannot be used as base-course material under Air Force airfield pavements.
- TM 3-34.64 (25 Sep 2012), paras 9-66 and 9-67
- 12N deep dive: What types of bituminous-stabilized soils are used, and which binders are preferred?
- Types include soil bitumen (a cohesive soil made water-resistant by admixture), sand bitumen (sand cemented by bituminous material), oiled earth (a sprayed slow- or medium-curing liquid asphalt that resists water absorption and abrasion), bitumen-waterproofed mechanically stabilized soil (blended soils compacted with comparatively small amounts of bitumen), and a bitumen-lime blend (small percentages of lime mixed with fine-grained soils to help bitumen penetrate and mix). Stabilization is generally done with asphalt cement, cutback asphalt, or asphalt emulsions. The type depends on the soil, the construction method, and the weather. Avoid tar as a binder in frost areas because of its high temperature susceptibility. The most satisfactory results generally come from using the most viscous liquid asphalt that can be readily mixed into the soil. For in-place work, liquid asphalts (cutbacks and emulsions) are applied directly and mixed and compacted immediately; emulsions are preferred over cutbacks because of energy constraints and pollution control.
- TM 3-34.64 (25 Sep 2012), paras 9-68, 9-70, and 9-71
- 12N deep dive: How does the USCS define particle sizes with sieves, and what are fines?
- Particles are defined by sieves—screens attached to metal frames. If a particle will not pass a particular opening, it is “retained on” that sieve. Passing a soil through several sieves breaks it into size groups. Coarse gravel is comparable to a lemon, egg, or walnut, and fine gravel is about the size of a pea. Sand ranges from rock-salt size through table salt or granulated sugar to powdered sugar. Below a Number 200 sieve, the particles (fines) are designated as silts or clays depending on their plasticity characteristics, not just size. The practical lower limit for sieves is the Number 200 sieve, with 0.074-millimeter-square openings. A particle about 0.07 mm is about as small as the unaided eye can detect.
- TM 3-34.64 (25 Sep 2012), paras 4-32, 4-33, and 4-35 and figure 4-3
- 12N deep dive: Why does the percentage of particles finer than 0.02 mm matter, and how is it measured?
- It has a direct bearing on the soil’s susceptibility to frost action. Distribution of sizes below the Number 200 sieve can be found by wet mechanical analysis (sedimentation): grains of different sizes fall through a liquid at different velocities. That test is not a normal field-laboratory test and is not particularly important in military construction except for this frost-susceptibility determination. A field method, called decantation, is given in TM 5-530.
- TM 3-34.64 (25 Sep 2012), para 4-35
- 12N deep dive: What are Hazen’s effective size and the coefficient of uniformity?
- Hazen’s effective size, D10, is the grain size corresponding to 10 percent passing on a grain-size distribution curve; it can be related to the permeability of clean sands and gravels. The coefficient of uniformity, Cu, is the ratio of the grain diameter corresponding to 60 percent passing (D60) to D10: Cu = D60/D10. Cu is used to judge gradation.
- TM 3-34.64 (25 Sep 2012), paras 4-42, 4-43, and 4-45 and figure 4-5
- 12N deep dive: What makes a soil well-graded or poorly graded, and why is well-graded material preferred?
- A well-graded soil has a good representation of all particle sizes from largest to smallest, and its grain-size curve is “smooth.” In the USCS, well-graded gravels must have Cu greater than 4, well-graded sands must have Cu greater than 6, and both must have a coefficient of curvature (Cc) from 1 to 3; sands and gravels that do not meet those conditions are poorly graded. Poorly graded soils are either uniformly graded (particles of nearly the same size) or gap-graded (large and small particles with some sizes missing). Well-graded coarse materials are usually preferable for bearing because good gradation gives high density and stability: smaller particles fill the voids between larger ones, interlocking the grains, improving load distribution downward, and reducing the tendency for individual grains to displace.
- TM 3-34.64 (25 Sep 2012), paras 4-48 through 4-50 and 4-52 and figures 4-6 through 4-8
- 12N deep dive: What specific-gravity values are typical for soils?
- Specific gravity (G) is the ratio of the material’s weight per unit volume at a stated temperature (usually 20 degrees Celsius) to that of water. The solids of most inorganic soils vary between 2.60 and 2.80. Tropical iron-rich laterite soils generally have a specific gravity of 3.0 or more, and clays can be as high as 3.50. Most soil minerals are greater than 2.60, so smaller values indicate the possible presence of organic matter.
- TM 3-34.64 (25 Sep 2012), paras 4-63 and 4-64
- 12N deep dive: How is soil moisture content defined, and what is oven-dry soil?
- Moisture content (w), expressed as a percentage, is the ratio of the weight of the water to the weight of the solids. It may exceed 100 percent. By definition, when a soil mass is dried to constant weight in an oven maintained at a temperature of 105 + 5 degrees Celsius, the weight of water is zero and the soil is said to be oven dry or dry. If a dried mass is cooled in contact with the atmosphere, it absorbs some water, called hygroscopic moisture.
- TM 3-34.64 (25 Sep 2012), paras 4-71 and 4-72
- 12N deep dive: What is unit weight (density), and what wet-density ranges are typical?
- Unit weight is the weight per unit volume of a soil mass; in soils terminology, “unit weight” and “density” are used interchangeably. Wet unit weight (wet density) applies when moisture content is anything other than zero. Depending on denseness and gradation, a sandy soil may have a wet density of 115 to 135 pounds per cubic foot; some very dense glacial tills may be as high as 145 pcf; and most clays range from 100 to 125 pcf. Dry unit weight (moisture content zero) is normally used in construction problems. Density can be greatly increased by compaction; in foundation problems, density is expressed as wet unit weight. A soil is saturated when the degree of saturation S equals 100 percent (all void volume filled with water).
- TM 3-34.64 (25 Sep 2012), paras 4-69 and 4-73 through 4-77
- 12N deep dive: What is plasticity, and how do cohesive and cohesionless soils differ?
- Plasticity is the ability of a soil to deform without cracking or breaking. Clays, whose adsorbed water films are relatively thick compared with particle size, are plastic over a wide range of moisture contents. Clean sands and gravels are nonplastic, and silts are essentially nonplastic because they are usually made of bulky grains (they may be slightly plastic if platy grains are present). A plasticity index is used to determine if soils are cohesive. Not all plastic soils are cohesive. Wet clays can be molded into various shapes and retain them. Gravels, sands, and most silts are cohesionless: they cannot be molded into a permanent shape and have little or no strength when dry and unconfined, though some may show slight “apparent cohesion” when damp because of surface tension in water films.
- TM 3-34.64 (25 Sep 2012), paras 4-86 and 4-87
- 12N deep dive: How do residual soils differ from the transported soils a military engineer usually encounters?
- Residual soils form where rock has been weathered in place, with chemical weathering usually dominant. The upper layers are usually fine-grained and relatively impervious, with a zone of partially disintegrated parent rock beneath that may crumble easily and break down under loads, abrasion, or further weathering. Lateritic soils (highly weathered tropical soils with significant iron, or iron and aluminum) are residual. Residual soils generally present drainage and foundation problems and are characteristically erratic and variable. By far most soils a military engineer encounters are transported and deposited at a new location by glacial ice, water, or wind, producing glacial, sedimentary (water-laid), and eolian (wind-laid) deposits.
- TM 3-34.64 (25 Sep 2012), paras 4-19 through 4-21
- 12N deep dive: What are the Atterberg (consistency) limits?
- They are the moisture-content boundaries between the states a fine-grained soil can exist in, depending on how much water it contains. They are also called consistency limits, after the Swedish soil scientist Atterberg, who first defined them in 1908. The shrinkage limit is the boundary between the semisolid and solid states, the plastic limit (PL) between the semisolid and plastic states, and the liquid limit (LL) between the plastic and liquid states. Above the LL the soil is presumed to behave as a liquid. The numerical difference between the LL and the PL is the plasticity index (PI), the range of moisture content over which the soil is plastic. These limits are important index properties used in classification, identification, and specifications that control the properties, compaction, and behavior of soil mixtures.
- TM 3-34.64 (25 Sep 2012), para 4-93
- 12N deep dive: How are the liquid limit and plastic limit tested?
- The limits are defined by standardized test procedures performed on the portion of the soil that passes the Number 40 sieve, sometimes called the soil binder, with the soil in a disturbed condition. The liquid limit is the minimum moisture content at which a soil will flow under a very small shearing force (with only a small energy input, it will flow under its own weight); in the laboratory it is usually found with a mechanical liquid-limit device. The plastic limit is arbitrarily defined as the lowest moisture content at which a soil can be rolled into a thread 1/8 inch in diameter without crushing or breaking. Above the PL a thread may be rolled thinner than 1/8 inch; below it the soil crumbles. At the PL, a hand-rolled thread reaches 1/8 inch and then crumbles or breaks into pieces 1/8 to 3/8 inch long when further rolling is attempted. Clean sands are nonplastic and the PL cannot be determined; they progress immediately from the semisolid to the liquid state.
- TM 3-34.64 (25 Sep 2012), paras 4-94 through 4-96 and figure 4-15
- 12N deep dive: How is the plasticity index calculated, and what does a high PI indicate?
- The PI is the numerical difference between the liquid limit and the plastic limit (PI = LL − PL). For example, if a soil has an LL of 57 and a PL of 23, the PI equals 34. Sandy soils and silts have characteristically low PIs, while most clays have higher values. Soils with high PI values are highly plastic and are generally highly compressible and highly cohesive. PI is inversely proportional to permeability. Soils that do not have a plastic limit, such as clean sands, are reported as having a PI of zero.
- TM 3-34.64 (25 Sep 2012), para 4-97
- 12N deep dive: How do kaolinite and montmorillonite clays differ, and what is bentonite used for?
- Both are clay minerals with laminated crystalline structures, but they behave differently. Kaolinite has a very rigid structure and tends to shrink and swell much less with changes in moisture. Montmorillonite can swell by taking water directly into its lattice and later decrease in flake thickness as water is squeezed out during drying, so it is subject to detrimental shrinkage and expansion; most montmorillonites also have much thicker films of adsorbed water. Bentonite is largely made of montmorillonite and, because of its swelling, is widely used commercially in slurry walls and temporary dam cores.
- TM 3-34.64 (25 Sep 2012), para 4-88
- 12N deep dive: What are shrinkage, slaking, and the bulking of sands?
- Shrinkage is a reduction in volume as moisture content drops, most pronounced from complete saturation to a very dry condition, and is greatest in clays—some show a 50 percent or more volume reduction from saturated to oven-dry. Sands and gravels generally show little or no volume change, except for bulking. If water is again made available to a still-saturated clay that has shrunk, it may swell; if expansion is restricted, as by a concrete pavement, the force may crack the pavement. If water is added after the soil has dried below the shrinkage limit, the mass generally disintegrates or slakes (a piece of dry clay in a glass of water usually falls completely apart in minutes). Construction problems are generally solved by removing such soils or preventing excessive moisture change. Bulking occurs in dry or nearly dry sand when a slight amount of moisture is introduced and the soil is disturbed: surface tension pulls the grains together and inhibits compaction, so slightly moist sands can have lower compacted densities than totally dry or saturated sands. Adding enough water to saturate the sand eliminates surface tension so it can be compacted to its densest configuration (the U-shaped compaction curve of free-draining soils).
- TM 3-34.64 (25 Sep 2012), paras 4-90 through 4-92 and figure 4-14
12N – Deep Dive: Grade Stakes, Earthwork, Drainage, Geotextiles & Field Tests
Source: TM 3-34.55 (Construction Surveying, 3 Aug 2012); TM 3-34.64 (Military Soils Engineering, 25 Sep 2012); TM 3-34.43 (Materials Testing, 3 Apr 2015); TM 3-34.62 (Earthmoving Operations, 30 May 2025 incl. C1, 29 Jul 2026). Complements mos-12n, mos-12n-3, and mos-12n-4; does not repeat those cards. Verify current editions.
- 12N deep dive: How is a road centerline stationed, and what is a plus station?
- The centerline starts at station 0+00. Stations are numbered consecutively and set at full 100-foot or 30-meter stations. Stakes are also set at important points such as culvert locations, road intersections, beginnings and ends of curves, or breaks in the grade. When measurements are in feet, those in-between points are numbered from the last full station and are called plus stations. Station 4+44.75 is 44.75 feet from station 4+00 and 444.75 feet from the beginning of the project. In the metric system, a point 135.56 meters from the start is simply numbered 135.56.
- TM 3-34.55 (3 Aug 2012), paras 2-20 and 2-21
- 12N deep dive: What do profile and cross-section levels provide for a road project?
- After the centerline, including horizontal curves, has been staked, elevations are taken along the centerline and laterally across the road. Plotting the centerline elevations produces a profile, from which the design engineer determines the grade of the road. Cross-section elevations, taken at right angles to the centerline at regular stations, plus stations, and intermediate ground breaks, are plotted to determine the volume of earthwork to be moved. The interval usually matches the station interval, but shorter intervals may be needed where the terrain changes abruptly.
- TM 3-34.55 (3 Aug 2012), paras 2-23 through 2-25
- 12N deep dive: How far ahead of construction should alignment and grade stakes be kept?
- The construction layout provides the alignment, grades, and locations that guide clearing, grubbing, stripping, drainage, rough grading, finish grading, and surfacing. Surveyors must stay far enough ahead in time and distance so construction is not interrupted. Suggested distances are: keep the centerline established 1,500 feet (450 meters) ahead of clearing and grubbing; keep rough grade established and slope stakes set 1,000 feet (300 meters) ahead of stripping and rough grading; and set stakes to exact grade 500 feet (150 meters) ahead of finish grading and surfacing. A hasty alignment marked by flags and rods can guide clearing and grubbing, but a deliberate centerline location is required for final grading and surfacing.
- TM 3-34.55 (3 Aug 2012), paras 2-27 and 2-28
- 12N deep dive: How is the cut or fill at a grade stake computed, and how is the stake marked?
- Grade stakes show the exact grade elevation to the construction force. The amount of cut or fill equals the grade rod minus the ground rod. Grade rod is the height of instrument minus the subgrade elevation at the station; the ground rod is the foresight reading at the station. A positive result is cut; a negative result is fill. Example: with a height of instrument of 115.5 feet, a subgrade elevation of 108.6 feet, and a ground-rod reading of 3.1 feet, the grade rod is 6.9 feet and cut or fill is +3.8 feet, a cut of 3.8 feet, marked on the back of the stake as C38. Rod readings and computations for these preliminary stakes are normally to the nearest 0.1 foot or 0.01 meter. The number under the cut or fill is the stake’s distance from the road centerline. Stakes may also be marked to the nearest whole or half foot to help the earthmoving crew.
- TM 3-34.55 (3 Aug 2012), paras 2-30 through 2-33 and figure 2-1
- 12N deep dive: Who decides how many grade stakes are required during rough grading, and when must all grade lines be staked?
- During rough grading, the construction crew determines grades for the edges of the traveled way, roadbed, and ditch lines. If the road is to be superelevated or is in rough terrain, the survey crew must provide stakes for all grade lines: centerline, edges of the traveled way, edges of the roadbed, and possibly ditch centerlines. Those stakes are offset so they will not be destroyed during grading. The construction foreman, not the surveyor, decides how many grade stakes are required and where.
- TM 3-34.55 (3 Aug 2012), para 2-34
- 12N deep dive: How are final grade stakes (blue tops) set after rough grading?
- The surveyor computes the final-grade rod reading, sets that reading on a rod target, and holds the rod on top of the stake. The stake is driven until the horizontal crosshair bisects the target, so the top of the stake is at final grade. The top is then marked with a blue lumber crayon to distinguish it from other stakes. Blue tops should be provided on all grade lines, but the construction foreman makes the final decision on which stakes are required. Final-grade rod readings and computations are normally to 0.01 foot or 0.001 meter. Where stakes cannot be driven, as in hard coral or rock, markings are often cut or crayon-marked on the rock itself.
- TM 3-34.55 (3 Aug 2012), paras 2-35 through 2-37
- 12N deep dive: What do slope stakes show, and how is their distance from centerline found on level ground?
- Slope stakes mark where cut or fill slopes intersect the natural ground and thus show the earthwork limits on each side of the centerline. When the ground is level across the road, the cut or fill at the slope stake is the same as at the center except for the addition of the crown, and both sides are the same distance out. On a fill, that distance is the center cut or fill times the side-slope ratio (horizontal to vertical), plus one-half the roadbed width. On a cut, it is the slope ratio times the center cut, plus the distance from the centerline to the outside edge of the ditch. On a superelevated section a widening factor must also be added, and the two sides will not be the same distance from the centerline.
- TM 3-34.55 (3 Aug 2012), paras 2-38 through 2-40
- 12N deep dive: How are slope stakes marked, and what do the numbers mean in the TM 3-34.55 cut-section example?
- On slope stakes, the cut or fill and the distance out from the centerline are written facing the center of the road; the backs show the station and the slope ratio to be used. In the cut-section example, the height of instrument is 388.3 feet and the subgrade is 372.5 feet, so the grade rod is +15.8 feet. A ground-rod reading of 6.3 feet at the center stake gives a center cut of 9.5 feet (15.8 − 6.3). The stake location on sloping ground is found by trial and error until the measured distance out equals the cut (or fill) at that point times the slope ratio, plus the ditch or half-roadbed width. When the measured and calculated distances agree (to about a tenth of a foot), the stake is set and marked—for example C69 for a 6.9-foot cut. A minus result, as when the ground rod is larger than the grade rod, indicates fill.
- TM 3-34.55 (3 Aug 2012), paras 2-41 through 2-47 and figures 2-2 through 2-4
- 12N deep dive: How should culvert sites be staked for the construction crew?
- The surveyor locates the intersection of the roadway centerline and a line defining the culvert direction; culverts are generally designed to follow natural drainage lines. Stakes mark the inlet and outlet points, and any needed cut or fill is marked on them. Alignment and grade stakes are set on the centerlines beyond the work area so a line stake that is disturbed or destroyed can be replaced easily. A benchmark should also be set near the site but outside the work area so grades can be reestablished.
- TM 3-34.55 (3 Aug 2012), paras 2-49 and 2-50 and figure 2-6
- 12N deep dive: Why must earthwork quantities and cut-and-fill locations be known before a horizontal-construction job is scheduled?
- Moving large volumes of earth is one of the most important operations in road, railroad, and airfield construction. To plan the schedule, the quantities of clearing, grubbing, and stripping, and the quantities and positions of cuts and fills, must be known so the most efficient type and number of earthmoving machines can be chosen, the proper number of personnel assigned, and the appropriate time allotted. Earthwork computations include volumes or quantities, final grades, balancing cuts and fills, and planning the most economical haul. Cross-section areas enclosed by the existing ground and the proposed cut or fill, together with measured distances along the centerline, are used to compute the volumes.
- TM 3-34.55 (3 Aug 2012), paras 4-1 through 4-3
- 12N deep dive: How are side slopes on a road or airfield cross section expressed, and why might a cut slope be flattened beyond what the soil requires?
- Side slopes are expressed as a ratio of horizontal distance to vertical distance. A 1 ½:1 side slope extends 1 ½ feet horizontally per foot of vertical rise or fall. Slopes may also be 3:1, 2:1, or 1:1. The surveyor usually takes the slope from the design specifications, based on the stability of the soil in cut or fill, but economy must often be considered. Cut slopes may be flattened more than the soil requires solely to produce enough material for a nearby fill, which can be more economical than opening a borrow pit.
- TM 3-34.55 (3 Aug 2012), para 4-7
- 12N deep dive: How are cross-section areas computed for earthwork volumes, and how must cut and fill be treated when both appear in the same section?
- Areas may be found by counting squares, by the geometric (trapezoidal) method, by the stripper method, or by the double-meridian-distance method. Counting squares and the stripper method are simple and approximate; the geometric and double-meridian-distance methods are as accurate as the cross-section field data will permit. Standard practice requires that cut and fill areas of a cross section, when both occur at the same time, be determined separately. When counting squares, count the squares enclosed by the section and multiply by the area one square represents, watching the horizontal and vertical scales (for example, 1 inch = 10 feet both ways is 100 square feet per inch square, but 1 inch = 10 feet horizontal and 1 inch = 2 feet vertical is only 20 square feet).
- TM 3-34.55 (3 Aug 2012), paras 4-5, 4-6, and 4-8 through 4-10
- 12N deep dive: How does TM 3-34.55 classify excavated material?
- Excavated material is usually classified as common excavation, loose rock, or solid rock. Common excavation is the moving of earth, or of earth with detached boulders less than one-half cubic yard in volume. Loose-rock excavation is consolidated material that has been loosened without blasting, using picks, bars, or simple air and mechanical devices. Solid-rock excavation is rock from solid beds, or boulders of 1 cubic yard or more, broken up by explosives. These types must be recorded separately in the field notes so excavation records match the construction work.
- TM 3-34.55 (3 Aug 2012), paras 4-26 and 4-27
- 12N deep dive: When is a borrow pit used, and how is the volume removed from it measured?
- When cuts and fills are out of balance, fill dirt is often borrowed from pits outside the construction limits but near the fill site. Whenever the haul from the last available dirt to the fill site becomes too far, it is cheaper to establish a borrow pit. Volume can be measured by staking a grid over the area (for example, 10-, 25-, 50-, or 100-foot squares), determining the elevation of each grid corner by leveling, then later reestablishing the corners and subtracting the average elevation after excavation from the average elevation before excavation and multiplying the difference by the area of the grid square. Two baselines parallel to adjacent sides of the grid, set outside the excavation but close enough to be convenient, are used to reestablish the grid. Waste areas or dumps of excess material are treated the same way, except the volume measured is the volume deposited, not excavated.
- TM 3-34.55 (3 Aug 2012), paras 4-28 through 4-32 and figure 4-7
- 12N deep dive: Why is drainage so important during road and airfield construction?
- Inadequate drainage causes most road and airfield failures. Proper drainage is of primary importance to operational requirements and to the useful life of an installation; poor drainage results in mud, washouts, and heaves that are expensive in delays and repairs to both roads and vehicles. Temporary drainage during construction also cannot be ignored, because standing water or saturated working areas can delay the job. The surveyor must anticipate drainage problems and gather enough field data for the best design and location of drainage structures.
- TM 3-34.55 (3 Aug 2012), paras 2-51 through 2-53
- 12N deep dive: What is the water table, and how high can capillary moisture rise in different soils?
- The water table is the contact between the zone of aeration and the zone of saturation; it fluctuates with recharge and outflow. In the zone of saturation all pores are filled with water. When that saturated zone is under no pressure except the atmosphere, the water is called free, or gravitational, water, and its movement through the soil is often termed seepage. Dry soil grains also attract moisture by capillary action. Because pore openings vary with grain size, a fine-grained soil develops a higher capillary fringe than a coarse-grained soil. In clays, capillary water sometimes rises as high as 30 feet, and in silts often as high as 10 feet; in coarse sands and gravels the rise may be from practically zero to a few inches.
- TM 3-34.64 (25 Sep 2012), paras 7-14, 7-15, 7-17, and 7-18 and figure 7-1
- 12N deep dive: Why can moisture accumulate under an impervious pavement, and how can that capillary water be controlled?
- If the water table is closer to the surface than the height of capillary rise, water is brought up to replace what evaporates. An impervious pavement reduces the effect of wind and temperature, so moisture accumulates and may reduce shearing strength or cause swelling, especially in fine-grained soils or coarse soils with detrimental plastic fines. Control methods include excavating the capillary-susceptible material and replacing it with granular soil (often justified only where frost is a factor); including a base that is unaffected by capillary action to interrupt the flow (a usual function of the base in a flexible pavement), draining the base if needed; lowering the water table with side ditches or subdrains, which works best in relatively pervious soils; or building the road or runway on a shallow fill of material not subject to detrimental capillarity, normally keeping the bottom of the base a minimum of 3 or 4 feet above the natural ground. A sand blanket or a geotextile fabric may be used to intercept capillary moisture and keep it out of the base course.
- TM 3-34.64 (25 Sep 2012), paras 7-19 and 7-26 through 7-29 and figures 7-2 and 7-3
- 12N deep dive: How does soil permeability affect drainage, and how do sands and clays differ?
- Permeability is the property of soil that permits water to flow through it. That movement is frequently termed seepage or percolation. Clean sands and gravels offer comparatively little resistance and are said to be permeable or pervious. Fine-grained soils, particularly clays, offer great resistance and are relatively impermeable or impervious, although some water still moves through them. Permeability reflects how easily a soil can be drained, so soils are sometimes classed as well-drained, poorly drained, or impervious. Permeability is closely related to frost action and to the settlement of soils under load.
- TM 3-34.64 (25 Sep 2012), para 7-33
- 12N deep dive: How should filter material be placed around a subsurface drain, and what failures does a poor filter cause?
- A layer of filter material approximately 6 inches deep should be placed around all subsurface piping systems. The proper filter largely determines the success or failure of the drainage system. An improper filter can make the system inoperative in one of three ways: the pipe may become clogged by small soil particles; particles from the protected soil may move into or through the filters, causing surface instability; or free groundwater may be unable to reach the pipe. Filter criteria are based on the soil’s gradation curve. If a mechanical analysis of the available filter and protected soils cannot be obtained, experience indicates that a well-graded concrete sand is satisfactory as a filter in most sandy, silty soils.
- TM 3-34.64 (25 Sep 2012), paras 7-40, 7-41, and 7-45 and figure 7-4
- 12N deep dive: What is frost action, and why does frost heave far exceed the 9 percent expansion of freezing water?
- Frost action is any process of freezing or thawing that affects a soil’s ability to support a structure. Pavements are frequently broken up as subgrades freeze in winter and thaw in spring, and in severe cases facilities have been closed until the subgrade recovered its stability. Early theories blamed heave on the expansion of water already in the soil voids, which would be only about 9 percent of the frozen-layer thickness. Heaves as great as 60 percent are not uncommon, and laboratory heaves of as much as 300 percent have been recorded, so the extra volume comes from additional water drawn from unfrozen layers and frozen into ice lenses at the plane of freezing temperatures. Thin films of water on soil grains can become supercooled (remain liquid below 32 degrees Fahrenheit), flow by capillary action to already-formed crystals, and freeze on contact, so an ice lens grows until the water supply is cut off or the temperature rises.
- TM 3-34.64 (25 Sep 2012), paras 7-53, 7-54, 7-56, and 7-57 and figure 7-6
- 12N deep dive: Why is a top-down spring thaw more damaging to a road or airfield than thawing from the bottom up?
- When the air stays barely below freezing long enough, deeply frozen soil thaws from the bottom upward because of heat from the earth’s interior (a snow blanket encourages this). Melted water from ice lenses can then seep back to the water table, so there is little saturation of the subgrade and unpaved roads stay more nearly passable. If the surface temperature rises well above freezing and stays there, thawing proceeds from the top downward and leaves a frozen, impervious layer beneath. The thawed soil between the pavement and that frozen layer is supersaturated, cannot drain, loses stability, and accounts for many pavement failures; unsurfaced earthen roads may become impassable. Thawing from both top and bottom also reduces stability, but for a shorter time than a top-only thaw. Winters with fluctuating early-season temperatures produce more damaging heaves than extremely harsh winters, because in a harsh winter the water is more likely to freeze in place before ice lenses can grow.
- TM 3-34.64 (25 Sep 2012), paras 7-58 through 7-61
- 12N deep dive: What conditions are needed for ice lenses to form, and which soils are generally frost susceptible?
- Temperatures below 32 degrees Fahrenheit must penetrate the soil, and a source of water must be available. That water may come from a high groundwater table, capillary supply from an adjoining water table, infiltration at the surface, a water-bearing aquifer, or voids of fine-grained soils. Inorganic soils containing 3 percent or more by weight of grains finer than 0.02 mm in diameter are generally considered frost susceptible. Frost-susceptible soils are classified in groups F-1 through F-4, listed approximately in order of increasing susceptibility to frost heaving or weakening as frost melts; F-4 soils are of especially high frost susceptibility. Silt soils, silty sands, and silty gravels tend to exhibit the greatest frost heave, because ice lenses grow more readily as grain size decreases, but the rate of water flow toward the freezing zone also decreases, so intermediate grain sizes are the worst.
- TM 3-34.64 (25 Sep 2012), paras 7-61 through 7-66 and 7-70
- 12N deep dive: How do uniform and nonuniform frost heave differ, and what site conditions make heave irregular?
- Frost heave is the raising of the pavement and is visible evidence that ice lenses have formed in the subgrade. Uniform heave raises adjacent areas by about equal amounts, so the surface’s initial shape and smoothness remain substantially unchanged; it may occur where stripping or fill depth, depth to groundwater, and soil characteristics are fairly uniform. Nonuniform (irregular) heave leaves objectionable unevenness or abrupt grade changes and typically occurs where the subgrade varies between clean sand and silty soils, or at abrupt transitions from cut to fill with groundwater close to the surface. Lateral drains, culverts, or utility lines under pavements on frost-susceptible subgrades frequently cause abrupt differential heaving and, wherever possible, should not be placed under those pavements, or transitions should be provided.
- TM 3-34.64 (25 Sep 2012), paras 7-68, 7-69, and 7-71 through 7-73
- 12N deep dive: Why does a frost-susceptible subgrade lose strength during a thaw, even if little heave is visible?
- When ice segregation has occurred, pavement load-supporting capacity drops during prolonged frost-melting periods because near-surface ice melts and water from melting snow or rain may infiltrate, leaving excess water that cannot drain through still-frozen soil below or through the shoulders. The soil is thus softened. Clay subgrades may lose supporting capacity even without significant heave, because water for ice lenses is drawn from the clay lattice below and the resulting shrinkage largely balances the volume of the ice. Traffic may remold the soil or develop hydrostatic pore pressure and further reduce strength. The degree and duration of the loss depend on the type of soil, temperatures during freezing and thawing, the amount and type of traffic during melting, the availability of water, and drainage conditions.
- TM 3-34.64 (25 Sep 2012), paras 7-74 through 7-76
- 12N deep dive: What four primary functions do geotextiles serve in horizontal construction?
- Reinforcement, separation, drainage, and filtration. Using these fabrics can replace soil and save time, materials, and equipment costs. In theater-of-operations horizontal construction, the primary concern is separating and reinforcing low load-bearing soils to reduce construction time. For reinforcement, the fabric lends its tensile strength to the soil and can often decrease the amount of subbase and base-course material required on low load-bearing soils. Swamps, peat bogs, and beach sands can also be quickly stabilized with geofabrics; tank trails have been successfully built across peat bogs using commercial geofabric.
- TM 3-34.64 (25 Sep 2012), paras 11-1 through 11-4 and figure 11-1
- 12N deep dive: How does a geotextile stop “pumping” when a road is built across soft soil?
- Building directly on weak soil usually requires a very thick base, and the solution is temporary: a pumping action causes fines to intrude into the base course, the base sinks into the weak soil, and more material has to be dumped on the site. Bypass may be blocked by the tactical situation; “mucking” (remove and replace) works only if good soil lies underneath and suitable fill is nearby; and mechanical or admixture stabilization can be slow and costly. In the last three of those options, poor soil eventually intrudes into the base or simply moves under load. A geotextile separates and confines the poor soil so it cannot intrude into a granular subbase or be lost.
- TM 3-34.64 (25 Sep 2012), paras 11-5 through 11-10 and figures 11-2 and 11-3
- 12N deep dive: How do geotextiles work in drainage and filtration applications?
- When placed so water is transmitted in the plane of the fabric, a geotextile provides a drainage function—for example, as a substitute for granular material in trench drains, blanket drains, and drainage columns next to structures. Woven fabric offers poor drainage characteristics; thick nonwoven fabrics have considerably more void space available for water transmission. A good drainage geotextile allows free water flow, but not soil loss, in the plane of the fabric. In filtration, the geotextile is placed in contact with the soil to be drained and lets water and suspended particles flow out while preventing unsuspended soil particles from being carried away. Filter fabrics are routinely used under riprap in coastal, river, and streambank protection and to line drainage ditches along a road pavement.
- TM 3-34.64 (25 Sep 2012), paras 11-11 and 11-12
- 12N deep dive: How does a geotextile change the permissible stress on a subgrade, and what wheel-load assumptions are used in the unpaved-road design method?
- Permissible stress (S) is the load that can be applied without causing the subgrade to fail. Without a geotextile, S = 2.8 times the soil’s shear strength C (in psi); with a geotextile, S = 5.0 times C. If C cannot be measured, a nomograph (figure 11-4) converts CBR or cone index to C. For design, both single and dual wheels are represented as single-wheel loads equal to one-half the axle load. A single wheel applies a contact pressure equal to the tire inflation pressure; dual wheels apply a pressure equal to 75 percent of the tire inflation pressure. Tandem axles exert 20 percent more than their actual weight on the subgrade because of overlapping stress from the adjacent axle. The design method assumes a good-quality aggregate with a minimum CBR of 80; if a lower-quality aggregate is used, the section thickness must be adjusted. The method also assumes 1,000 equivalent 18,000-pound vehicle passes; if more are anticipated, increase the design thickness by 30 percent and monitor performance.
- TM 3-34.64 (25 Sep 2012), paras 11-15 through 11-17, 11-21, and 11-23 and figure 11-4
- 12N deep dive: How do woven and nonwoven geotextiles differ, and which is usually stronger?
- Woven fabrics have filaments woven into a regular, usually rectangular, pattern with fairly evenly spaced and sized openings. Nonwoven fabrics have filaments connected other than by weaving, typically by needle punching or heat bonding at intersection points, and the pattern and openings are irregular. Woven fabrics are usually stronger than nonwoven fabrics of the same fabric weight. Woven geotextiles typically reach peak strength at between 5 and 25 percent strain, while nonwoven fabrics have a high elongation of 50 percent or more at maximum strength. Equipment ground pressure is an important factor in choosing fabric thickness: a thicker fabric is necessary to stand up to high equipment ground pressure.
- TM 3-34.64 (25 Sep 2012), paras 11-26 and 11-27 and table 11-5
- 12N deep dive: How should a site be prepared and a geotextile laid for an unpaved road or airfield?
- Clear, grub, and excavate to design grade, and fill ruts and surface irregularities deeper than 3 inches. If the soil is CBR 1, lightly compact the subgrade to help locate unsuitable materials that may damage the fabric, and remove those materials when practical. Over extremely soft soils such as peat bogs, disturb the surface root mat as little as possible; cover protruding roots, stumps, or stalks with sand or sawdust to cushion the geotextile. Nonwoven geotextiles, with their high elongation, are preferred when the surface is uneven. Roll the fabric out by hand, ahead of backfilling and directly on the subgrade, commonly in the direction of the roadway (or cut and laid transverse if large areas cannot be leveled). Avoid large wrinkles. Overlap multiple widths; recommended minimum overlap is 1 to 1.5 feet when CBR is greater than 2, 2 to 3 feet when CBR is 1 to 2, 3 feet or sewn when CBR is 0.5 to 1, and sewn when CBR is less than 0.5. All roll ends should be overlapped 3 feet or sewn.
- TM 3-34.64 (25 Sep 2012), paras 11-29 through 11-32, figure 11-8, and table 11-7
- 12N deep dive: How should base material be placed on a geotextile so the fabric is not damaged?
- If angular rock will form the base, first place a protective layer of 6 to 8 inches of finer material. Then dump the base material onto the previously spread load, push it out over the fabric, and spread it from the center with a bulldozer. Vehicles must not drive directly on the fabric or puncture it. Small tracked bulldozers with a maximum ground pressure of 2 psi are commonly used, and the blade is kept high to avoid driving rock down into the fabric. Compaction and grading can then be done with standard compaction equipment. If the installation has side drains, build them after the pavement.
- TM 3-34.64 (25 Sep 2012), para 11-33
- 12N deep dive: What is a sand grid, and how is a sand-grid road built and used?
- A sand grid is a honeycomb-shaped plastic geocell in the Army inventory (NSN 5680-01-198-7955) used to expedite an expedient road on sand, such as a beach or desert. When fully expanded it measures 20 feet long, 8 feet wide, and 8 inches deep. It is very useful when developing a beachhead for logistics-over-the-shore operations. Construction can be done by a squad-sized element with a scoop loader, light bulldozers, and compaction equipment: lay out a centerline, level the roadway, distribute and expand the folded grids, secure them by filling end and some side cells with shovels, overfill the grids with a scoop loader, compact the sand, back-drag excess to the shoulders if a surface treatment will be applied, and, if available, apply an asphalt surface treatment to enhance service life. Sand grids perform well under wheeled traffic, but tracked-vehicle traffic is very destructive; an asphalt surface treatment reduces damage when a limited number of tracked vehicles must use the road. Damaged sections can be removed and a new grid fitted in place. Sand grids can also be used for bunkers, revetments, retaining walls, and other expedient structures.
- TM 3-34.64 (25 Sep 2012), paras 11-35 through 11-40 and figure 11-10
- 12N deep dive: What two factors have the greatest effect on cut- or fill-slope stability?
- Slope gradient and groundwater. Generally, the greater the slope gradient and the more groundwater present, the less stable a given slope will be, regardless of the geologic material or the soil type. Groundwater reduces stability because rising water exerts a buoyant (uplift) force that reduces the interlocking, or normal, force between grains. A dry clay can have considerable shear strength, but as it absorbs water its shear strength decreases.
- TM 3-34.64 (25 Sep 2012), paras 10-8, 10-17, and 10-20
- 12N deep dive: What is the most accurate way to determine soil moisture content, and how do oven-dry and microwave tests compare?
- The most accurate test is the oven-dry test in a thermostatically controlled oven. Drying soil in a frying pan or other container over an uncontrolled heat source is usually less accurate, because heating most soils to excessive temperatures can cause chemical changes that lead to errors. Results are recorded on DD Form 1205. When an average water content is reported, the individual tests must be within ± 1 percent; tests that do not meet that requirement are not used, and if none do, additional testing is required. For many field applications, a microwave is the most efficient expedient method: it gives results within 0.5 percent of the oven-dried value in 5 to 10 minutes, versus 4 to 16 hours in the oven-dry test. The microwave test is applicable for most soil types, but soils with excessive halloysite, mica, or montmorillonite, and highly organic soils, may not yield reliable water-content values. A brick or similar energy buffer must be placed in the microwave to absorb excess microwaves and prevent damage. For sands and gravelly soils, eye goggles are recommended because overdrying can burst individual grains.
- TM 3-34.43 (3 Apr 2015), paras 3-1, 3-3 through 3-6, and 3-8 through 3-9 (including the warning) and DD Form 1205
- 12N deep dive: How does the calcium carbide (Speedy) moisture test work, and when should it not be used?
- The 26-gram calcium carbide gas-pressure tester determines moisture content to within ± 0.5 percent. Calcium carbide reacts with water to produce acetylene gas, which is extremely flammable; avoid open flame when releasing the gas, and work in a well-ventilated area because asphyxiation could occur in a confined space. Because of the small sample, do not use the device on soils that contain material coarser than the Number 4 sieve (4.75 mm). High-plasticity clays or other soils that are not friable enough to break up may not give representative moisture contents because the reagent cannot mix well with the sample. A 26-gram sample and two 1 1/4-inch steel balls go in the tester body; about 24 grams (three scoops) of calcium carbide go in the cap; after sealing, shake at least 1 minute for granular soils and up to 3 minutes for other soils. Convert the highest gauge reading to oven-dry moisture using the calibration curve or conversion chart supplied with the tester, and check the gauge against a standard calibration kit.
- TM 3-34.43 (3 Apr 2015), paras 3-11 through 3-16 and 3-20 (including the danger note), figure 3-2, and table 3-2
- 12N deep dive: How does the sand-cone (sand-displacement) test measure in-place density?
- A sample is dug out, the volume of the hole is measured with calibrated sand, and the dry weight of the sample is determined. It may be used in fine- or coarse-grained materials and also to validate other in-situ density devices. Minimum test-hole volumes are 0.05 cubic foot for a maximum aggregate size of 1/2 inch, 0.075 cubic foot for 1 inch, and 0.10 cubic foot for 2 inches. The sand must be clean, dry, and free-flowing, passing the Number 10 sieve with less than 3 percent passing the Number 60 sieve; Ottawa sand (generally Number 20 to Number 40) is ideal. A double-cone cylinder permits calibrating the sand for each test. Results are recorded on DD Form 1215.
- TM 3-34.43 (3 Apr 2015), paras 8-1 through 8-5 and DD Form 1215
- 12N deep dive: When are the steel-shot and drive-cylinder methods used instead of a sand cone?
- The steel-shot replacement method is simpler and quicker because the shot is much less susceptible to densification changes with placement method, and volume can be read directly from marks on a graduated cylinder. It is intended to determine in-place density to within 2 percent, or ± 2.5 pounds per cubic foot for soils averaging 125 pcf, with no apparent bias versus the sand cone. For most expedient work the test cavity is on the order of 0.04 to 0.05 cubic foot (a 4-inch-diameter hole about 6 inches deep), which should approximate the thickness of a compacted lift. The drive-cylinder method tamps a steel cylinder of known volume into the ground, then the cylinder is dug out and the dry weight of the sample is determined, to within ± 2 pcf. It is useful in weaker soils and where a sand-cone or steel-shot hole cannot keep vertical side walls. It is not recommended in very hard natural soils, heavily compacted soils, or organic soils, and appreciable gravel larger than 3/16 inch may introduce significant error because of large voids in the extruded sample.
- TM 3-34.43 (3 Apr 2015), paras 8-10, 8-11, and 8-13 through 8-16
- 12N deep dive: How do nuclear and water-balloon (rubber-balloon) methods measure in-place density and moisture?
- A nuclear moisture-and-density tester determines dry density and moisture content; follow the equipment manufacturer’s manual, the Service’s radiation-protection requirements, and the Nuclear Regulatory Commission licensing agreement. The testers typically contain cesium, which emits gamma radiation that is counted after it passes through the soil and is translated into density, and americium mixed with beryllium, which emits neutrons that are moderated by collisions with hydrogen so moisture can be determined by counting hydrogen atoms. In the water-displacement method, a rubber balloon is placed in the sample hole and the volume of water needed to fill the balloon is read on a calibrated scale in cubic feet; an initial reading is taken before the sample is removed, then after the hole is dug the balloon is forced to conform to the hole contours and the difference in readings is the hole volume. Several manufacturers also make nonnuclear moisture-and-density devices, but the TM states that no formal military guidance has been provided to compare their effectiveness or limitations with the known test methods described in the manual.
- TM 3-34.43 (3 Apr 2015), paras 8-20 through 8-24
- 12N deep dive: When does a soil-aggregate mixture stay stable when wet, and what fines limit does TM 3-34.64 recommend?
- Gravel, broken stone, and crushed rock remain stable even with rain or ponding because their large particles are not separated or lubricated by moisture, so they do not suffer a severe loss of strength; they can even be compacted underwater, as in a river ford. If there are enough coarse particles to keep grain-to-grain contact, the fines between them often have only a minor effect and strength stays high when wet. If the coarse particles are not continuously in contact, the mixture loses strength with added water as though no aggregate were present. High-plasticity clays (PI greater than 15) in sand and gravel fills can expand on wetting, reduce grain-to-grain contact, lower strength, and increase differential movement. The change from stable to unstable can be subtle, even between two locations in a single borrow pit. To assure a stable material, the mixture should usually contain no more than about 12 to 15 percent by weight passing a Number 200 sieve, and the finer fraction should ideally show low plasticity (PI less than 5).
- TM 3-34.64 (25 Sep 2012), paras 12-1 and 12-2
- 12N deep dive: What are laterites and lateritic soils, and how can they harden into a usable road stone?
- They form a group of red, brown, and yellow residual soils, ranging from fine-grained material of light texture to nodular gravels and cemented soils, and from loose material to massive rock. They are characterized by iron and aluminum oxides or hydroxides, especially iron, which give the colors. For engineering purposes, “laterite” is confined to the coarse-grained vermicular concrete material, including massive laterite; “lateritic soils” have lower concentrations of oxides. Most laterites are already hardened, but some natural deposits that have not been exposed to drying are soft, clayey, and mottled (red, yellow, brown, purple, and white). When laterite is exposed to air or dried by lowering the groundwater table, irreversible hardening often occurs, producing a material suitable for building or road stone. Plinthite is a laterite rock that in place is soft enough to cut with a metal tool but hardens irreversibly when removed and dried, and it has potential use as a brick. Laterites and lateritic materials occur frequently in the tropics and subtropics, usually on level or gently sloping terrain with little mechanical erosion.
- TM 3-34.64 (25 Sep 2012), paras 12-3, 12-5, 12-6, and 12-8
- 12N deep dive: What special testing and compaction issues do laterites and lateritic soils present?
- Lateritic soils behave more like fine-grained sands, gravels, and soft rocks. Laterite typically looks porous or vesicular, and some particles crush easily under impact, disintegrating into a soil that may be plastic. Grain-size and Atterberg-limit results therefore depend on how the sample is treated, how much it is broken down, and how the minus Number 40 material is prepared; the more the structure is handled and disturbed, the finer the grading becomes and the higher the Atterberg limits. Laterites and lateritic soils can be stabilized with cement, asphalt, lime, or mechanical stabilization, but because characteristics vary widely, laboratory or preferably field tests must determine the agent and quantity for the particular soil. They can perform satisfactorily in a low-cost, unsurfaced road even with a higher percent of fines than is usual in the continental United States, believed due to the cementing action of iron oxide. Cement and asphalt work best at lower fines content; when fines are quite plastic, lime reduces plasticity. Field trials should find a compaction method that gives sufficient density without destroying the granule structure and cementation; generally, vibratory compaction is best. Laboratory programs for tropical conditions do not ordinarily include freeze-thaw tests but should check wetting and drying.
- TM 3-34.64 (25 Sep 2012), paras 12-7, 12-10, 12-11, 12-19, and 12-20
- 12N deep dive: How should desert soils be stabilized for roads and airfields, and what stabilizer often fails there?
- Because of wind erosion, desert soils tend to be granular (rock, gravel, or sand), and they often need stabilization to increase bearing capacity. Engineering methods that work in temperate or tropical regions are often ineffective on desert soils. The primary means are soil blending, geotextiles, and bituminous stabilization. Chemical admixtures generally perform poorly under desert conditions because they cease hydration or “set up” too quickly and therefore do not gain adequate strength. If a source of fines is located, they may be blended with the in-place soil after a complete soil analysis, and unusual climate over the design life must be considered. During Operation Desert Storm, many roads in Saudi Arabia were stabilized with a fine material known as marl; they performed well until seasonal rains occurred, then they failed.
- TM 3-34.64 (25 Sep 2012), paras 12-36 through 12-40
- 12N deep dive: What is a spill under TM 3-34.62, and what immediate actions should equipment crews take?
- A spill is any release of petroleum products exceeding 5 gallons, or any amount of hazardous waste, depending on local regulations (some states have stricter limits than 5 gallons). Protect yourself first: evacuate as appropriate to the type of spill, follow the material safety data sheet, use proper PPE, extinguish smoking materials and ignition sources, turn off power if fire is possible, ventilate the area, and shower and change clothes as soon as possible if hazardous-waste contamination occurs. Stop the flow if it can be done without unnecessary chances, injury, or contamination, by shutting off valves and turning drums upright. Contain the spill with absorbent or by making dams so it does not enter storm or sewer drains or other waterways; if it cannot be contained, divert the flow away from water sources. Report the spill to a superior, sound an alarm or give a verbal warning, keep assessing size and severity while another person calls the installation fire department, and report any hazardous material other than a petroleum product, regardless of quantity, to the unit environmental compliance officer or the installation environmental office immediately.
- TM 3-34.62 (30 May 2025 incl. C1, 29 Jul 2026), paras 14-3 through 14-7 and figure 14-1
- 12N deep dive: How is a surface-thawing index computed when designing a base to protect permafrost or a frost-susceptible subgrade?
- Increasing the depth of nonfrost-susceptible base-course material can prevent subgrade thawing; required thickness is taken from figure 12-2 using the thawing index. The surface-thawing index is computed by multiplying the air-temperature thawing index by a correction factor for the type of surface: 1.65 for bituminous surfaces and 1.5 for concrete. Thawing degree-days data is usually available from local weather stations or highway departments, or it can be estimated from the distribution figures in the TM.
- TM 3-34.64 (25 Sep 2012), paras 12-46 and 12-47 and figure 12-2
- 12N deep dive: How steep can laterite cuts be made?
- The stiff natural structure of harder laterites allows very steep or vertical cuts, perhaps to depths of 15 to 20 feet. Softer laterites and lateritic soils should be excavated on flatter than vertical slopes, but still appreciably steeper than the remolded frictional characteristics would indicate. It is important to prevent water from entering at the top of the slope.
- TM 3-34.64 (25 Sep 2012), para 12-21
- 12N deep dive: What are the three principal types of coral used in military construction, and how do they differ?
- Pit-run coral, coral rock, and coral sand. Pit-run coral is fragmented coral with sands and marine shells; at best it classifies as a soft rock even when most cemented, seldom shows cohesion, tends to be well graded, has CBR values that may vary between 5 and 70, and seldom reaches densities above 120 pcf. Coral rock is commonly found in massive formations: the white type is very hard, while the gray type tends to be soft, brittle, and extremely porous; CBR values vary from 50 to 100, and densities above 120 pcf are common except in some of the soft rock. Coral sand is decomposed coral rock, sometimes mixed with washed beach sands; it generally classifies as a poorly graded sand, seldom has more than 20 percent passing a Number 200 sieve, has CBR values between 15 and 50, and because of the lack of fines is hard to compact, so densities above 120 pcf are uncommon.
- TM 3-34.64 (25 Sep 2012), paras 12-22 through 12-26
- 12N deep dive: How is coral excavated, and what blasting method works best in hard coral rock?
- Coral may be obtained from construction-site cuts, quarries, and wet or dry borrow pits worked in benches. Use rooters to loosen softer deposits and move the material with bulldozers to power shovels for loading; rooting and panning are preferable in soft coral pits or shallow lagoons. Where little loosening is needed, draglines and carryall scrapers can be used. Coral from fringing reefs and lagoons can sometimes be dug by dragline or shovel, piled as a causeway, and then trucked away from the seaward end. Hard coral rock in cuts or aggregate quarries requires considerable blasting. Hard coral “heads” embedded in softer deposits are a hazard to equipment and also require blasting. Blasting hard coral differs from ordinary rock quarrying because of innumerable fissures and large voids; the porosity decreases blasting efficiency. Conventional use of low-percent dynamite in tamped holes produces the most satisfactory results. Shaped charges are ineffective, especially underwater, and cratering charges, though effective, are uneconomical. Holes are usually 8 to 12 feet deep on 4- to 8-foot centers.
- TM 3-34.64 (25 Sep 2012), paras 12-27 through 12-30
- 12N deep dive: How should coral be placed and compacted, and what happens if “live” coral is used?
- Selected coral stripped from lagoon or beach floors or quarried from sidehills is excellent for fills, subgrades, and base courses when properly placed. White or nearly white coral with properly proportioned granular sizes, compacted at optimum moisture, creates a concretelike surface, but the wearing surface needs heavy maintenance because coral breaks down and abrades easily under traffic, and it is also extremely abrasive to tires. Hard coral rock, properly graded, is a good concrete aggregate; soft coral rock makes inferior, low-strength, often honeycombed concrete, and hard coral rock should not be used as a wearing surface because it breaks with sharp edges that easily cut pneumatic tires—use tracked equipment as much as possible when working it. If coral is quarried from reefs or pits containing living deposits, aerate and dry it for 6 days if possible, but not less than 72 hours; living organisms can remain alive in wet stockpiles for up to 72 hours, and “live” coral exhibits high swell with loss of density and strength. Control moisture carefully: even a 1 percent increase above OMC can reduce densities 20 percent or more in certain types. Compact between OMC and 2 percent below OMC. Maintain coral roads when the coral is wet. Salt water, used in compaction whenever possible, gives higher densities with the same effort than fresh water.
- TM 3-34.64 (25 Sep 2012), paras 12-31 through 12-35
- 12N deep dive: What is the most effective way to stabilize desert soils for temporary roads and airfields?
- Bituminous treatment is the most effective method for temporary road and airfield use. Geotextiles can be used alone, such as the sand grid, or in combination with bituminous surfacing; the combination is the most effective.
- TM 3-34.64 (25 Sep 2012), paras 12-41 and 12-42
- 12N deep dive: How should roads and airfields be built over permafrost or thaw-unstable arctic soils?
- Construction in permafrost areas is more difficult than in temperate regions because the impervious permafrost produces poor drainage, and cuts change the subsurface thermal regime. If a frozen soil contains visible ice, or becomes unstable when a sample is thawed, it is thaw-unstable; cuts into those soils should be avoided, and if they cannot be avoided, substantial and frequent maintenance will be required. Cuts can generally be made into dry frozen (thaw-stable) soils—generally sands or gravels—without major problems. Depths of freeze and thaw are significantly altered by construction; clearing and stripping change the depth to permafrost. If the subgrade is thaw-stable, some thawing may be accepted because little settlement is expected. If it is thaw-unstable, a granular embankment 4 to 5 feet thick is generally adequate for all but the heaviest traffic, though considerable regrading is needed to keep a relatively smooth surface. Embankments only 2 to 3 feet thick have been used over geotextile layers that keep the fine-grained subgrade from contaminating the fill; more fill may be needed as thawing and settlement progress. It is usually desirable to leave the surface organic layer intact; small trees and brush should be cut and placed beneath the embankment as a barrier against mixing. Arctic and subarctic ecosystems are fragile and, unlike temperate ones, do not recover quickly—disturbance can continue to degrade the ground for decades.
- TM 3-34.64 (25 Sep 2012), paras 12-43 through 12-45 and 12-53 through 12-55 and figure 12-1
- 12N deep dive: How do the bite (grit) and feel tests help tell sand, silt, and clay apart in the field?
- In the bite test, grind a small pinch of soil lightly between the teeth (ideally material passing the Number 200 sieve). Sharp, hard sand particles grate very harshly and are highly objectionable, even in fine sands. Silt grains are much smaller, feel less harsh and not particularly gritty, but are still unpleasant and easily detected. Clay grains are not gritty; they feel smooth and powdery like flour, and dry lumps of clayey soil stick when lightly touched with the tongue. In the feel test, rub the fines between the fingers or on a more tender area such as the inside of the wrist: sand feels gritty; dry silts dust readily and feel soft and silky; clays powder with difficulty but feel smooth and gritless like flour. Consistency of an undisturbed lump squeezed between thumb and forefinger can be described as hard, stiff, brittle, friable, sticky, plastic, or soft. Clays that become fluid on remolding are probably near their liquid limit; if they remain stiff and crumble when reworked, they are probably below their plastic limit.
- TM 3-34.43 (3 Apr 2015), paras 1-58 through 1-62
- 12N deep dive: How is the roll or thread test done, and what do the results mean?
- Perform it only on material passing the Number 40 sieve. Mix the soil with water until it can be molded without sticking to the fingers (just below the sticky limit), shape it into a cylinder, and roll it on glass or heavy waxed paper into a thread about 1/8 inch in diameter. If it rolls into a thread, the soil has some plasticity; the number of times it can be rerolled without crumbling measures the degree of plasticity. Materials that cannot be rolled this way are nonplastic or of very low plasticity. If the soil can be molded into a ball or cylinder and deformed under very firm finger pressure without crumbling or cracking, it is CH. If it can be molded but cracks or crumbles without breaking up, it is of low plasticity (CL, ML, or MH). If it forms a soft, spongy ball or thread, it is organic (OL or OH). If it cannot be rolled into a thread at any moisture content, it is nonplastic (ML or MH).
- TM 3-34.43 (3 Apr 2015), paras 1-63 through 1-66 and figure 1-4
- 12N deep dive: How does the wet-shaking (dilatancy) test identify silts and fine sands?
- Perform it only on material passing the Number 40 sieve. Mold a ball about 3/4 inch in diameter, just wet enough that it will not stick to the fingers, smooth it in the palm, then shake it horizontally and strike the back of the hand vigorously against the other hand. A positive reaction is water coming to the surface with a smooth, shiny, “livery” appearance. When the sample is then squeezed, the surface water disappears, the surface becomes dull, and the material becomes firm and finally crumbles. Shaking reorients bulky, noncohesive grains, reduces voids, and forces water out; squeezing does the reverse, and the cycle can be repeated. A rapid reaction is typical of nonplastic fine sands and silts. A sluggish reaction indicates slight plasticity, as in some organic silts or silts with a little clay (even a small amount of clay greatly slows the reaction). No reaction does not prove the complete absence of silt or fine sand.
- TM 3-34.43 (3 Apr 2015), paras 1-68 through 1-71 and figure 1-5
- 12N deep dive: How does the breaking or dry-strength test distinguish clayey soils from silty soils?
- Perform it only on material passing the Number 40 sieve. Mold a pat about 2 inches in diameter and 1/2 inch thick in a wet, plastic state, let it dry completely, then try to break it and powder it between the fingers (use a fresh break, not a shrinkage crack). If the pat cannot be broken or powdered by finger pressure, it is a very highly plastic soil (CH). If it can be broken with great effort but cannot be powdered, it is highly plastic (CL). If it can be broken and powdered with some effort, it is medium-plastic (CL). If it breaks easily and powders readily, it is slightly plastic (ML, MH, or CL). If it has little or no dry strength and crumbles or powders when picked up, it is nonplastic (ML or MH) or organic (OL or OH).
- TM 3-34.43 (3 Apr 2015), paras 1-72 through 1-75 and figure 1-6
- 12N deep dive: What do the ribbon and shine tests show about a soil’s plasticity?
- Both are done on material passing the Number 40 sieve, prepared just below the sticky limit (the same as for the thread test). For the ribbon test, form a roll 1/2 to 3/4 inch in diameter and 3 to 5 inches long, then squeeze it over the edge of the hand into a flat, unsupported ribbon about 1/8 to 1/4 inch thick, making the longest ribbon the soil’s cohesion will support. If it holds together for more than 8 inches without breaking, it is a plastic soil with a high liquid limit (CH). If it can be ribboned only with difficulty into 3- to 8-inch lengths, it is low plasticity (CL). If it cannot be ribboned, it is nonplastic (ML or MH). In the shine test, a slightly moist or dry piece of CH produces a definite shine when rubbed with a fingernail or a smooth metal surface such as a knife blade; lean clay remains dull.
- TM 3-34.43 (3 Apr 2015), paras 1-77 through 1-80 and figure 1-7
12N Horizontal Construction Engineer: Final exam study guide
Source: DA Pam 611-21 ch. 10C (Oct 2026 copy), 10-12N para a and a(1)–(4). Complements existing 12N major-duties and split equipment and skill-level cards; does not repeat them word for word. No public STP or ICTL for 12N was on disk for this pass. No exam questions or passing scores are invented here. Public, unclassified sources only. Verify current editions.
- 12N (review): Besides serving as a member or supervisor of a squad, team, section, or platoon, how does DA Pam 611-21 describe the 12N duty path?
- Duties start with operating heavy equipment at an intern level and progress to senior equipment-operator level, with supervisory responsibilities for personnel, construction projects, obstacle emplacement, and counter-obstacle operations involving construction equipment.
- DA Pam 611-21 ch. 10C (Oct 2026 copy), 10-12N para a. Review of the major-duties sentence that is not on the existing one-line major-duties card.
- 12N (review): How do the skill level 1 intern-operator tasks in DA Pam 611-21 group together?
- The SL1 Soldier is an intern-level equipment operator with basic skill at interpreting grade stakes and identifying basic soil properties, and performs basic tasks on the crawler tractor, motorized scraper, scoop loader, motorized grader, hydraulic excavator, backhoe loader, dump truck, water distributor, rollers (sheep’s-foot, smooth-drum, and vibratory), and tractor-trailer used to transport heavy construction equipment.
- DA Pam 611-21 ch. 10C (Oct 2026 copy), 10-12N para a(1) (MOSC 12N1O). Ties the split SL1 equipment cards in mos-12n-3.txt together for review. The pamphlet has stray commas in this paragraph; they are omitted here.
- 12N (review): How do 12N duties change from skill level 1 to skill level 4 in DA Pam 611-21?
- SL1 is the intern-level operator described above. SL2 is a Horizontal Construction Sergeant with limited supervision of equipment and personnel, becomes a primary operator for finishing work and complex situations, and guides less-experienced operators on techniques, procedures, and operator maintenance. SL3 is a Horizontal Construction Supervisor or Section Sergeant who supervises heavy construction and lifting equipment, calculates equipment and operator requirements for project estimates, and organizes and directs mobility and countermobility missions. SL4 is a Senior Horizontal Construction Supervisor or Platoon Sergeant who organizes the overall construction workload, uses project-management techniques and coordinates supporting units, plans and supervises engineer construction-equipment operations including mobility and countermobility, and develops and executes a quality-control plan and standing operating procedures.
- DA Pam 611-21 ch. 10C (Oct 2026 copy), 10-12N para a(1)–(4) (MOSC 12N1O through 12N4O). Review summary only; the separate skill-level cards remain in mos-12n-3.txt and mos-12n-horizontal-construction.txt. The pamphlet prints “Organizes and direct”; this card uses directs.
12N – Horizontal Construction Engineer
Source: DA Pam 611-21 ch. 10C (Oct 2026 copy) (10-12N); DA Pam 611-21 ch. 10 MOS/skill-level classification listing (chapter-10-base); TM 3-34.62 (30 May 2025 incl C1); ATP 3-34.40 (14 Apr 2023); FM 3-34 (15 Dec 2025). Verify current editions.
- 12N: What is the primary role of the Horizontal Construction Engineer?
- Status: current MOS (DA Pam 611-21 ch. 10C). To operate heavy equipment (bulldozers, graders, scrapers, loaders, excavators, rollers) for earthmoving, road and airfield construction, and survivability positions.
- DA Pam 611-21 ch. 10C (Oct 2026 copy) (10-12N) paras a and a(1) (crawler tractor, scraper, scoop loader, grader, hydraulic excavator, backhoe loader, dump truck, roller); FM 3-34 (15 Dec 2025) para 2-62 (survivability positions)
- 12N: Where is 12N AIT?
- Fort Leonard Wood, MO – verify current length on goarmy.com.
- DA Pam 611-21 ch. 10C (Oct 2026 copy) (10-12N) para b(6) (course under the USA Engineer Center and School); 10C gives the USAES address as Ft Leonard Wood, MO (DA Pam 611-21 ch. 10C (Oct 2026 copy) (10-12D) para a; DA Pam 611-21 ch. 10C (Oct 2026 copy) (10-12P) para b(9)). Course length not in 10C
- 12N: What kinds of equipment does a 12N operate?
- Earthmoving and construction equipment such as dozers, graders, scrapers, loaders, excavators, compactors/rollers, and dump trucks (12N absorbed several former 21-series equipment operator specialties).
- DA Pam 611-21 ch. 10C (Oct 2026 copy) (10-12N) para a(1) (crawler tractor, motorized scraper, scoop loader, motorized grader, hydraulic excavator, backhoe loader, dump truck, water distributor, rollers, tractor trailer); DA Pam 611-21 ch. 10 MOS/skill-level classification listing (chapter-10-base) (21E1-2 and 21N3-4 converted to 12N, 01 Oct 2010)
- 12N: What does a grader do?
- Shapes and levels surfaces, crowns roads, and cuts ditches.
- TM 3-34.62 (30 May 2025 incl C1) ch. 4 introduction ("grading, shaping, bank sloping, and ditching"; also leveling and crowning)
- 12N: What does a scraper do?
- Cuts, loads, hauls, and spreads soil over medium distances.
- TM 3-34.62 (30 May 2025 incl C1) ch. 3 introduction (loading, hauling, dumping and spreading loose materials; "ideal for medium-haul earthmoving operations")
- 12N: What is compaction and why is it important?
- Increasing soil density with rollers to improve load-bearing strength and reduce settling.
- TM 3-34.62 (30 May 2025 incl C1) para 11-16 (mechanically densifying soil; enhances load-bearing capacity and minimizes settlement)
- 12N: What are survivability tasks 12Ns support?
- Digging vehicle fighting positions, protective berms, and trenches.
- FM 3-34 (15 Dec 2025) para 2-62 (survivability positions, individual and crew-served fighting positions, defilade fighting positions for combat vehicles); DA Pam 611-21 ch. 10C (Oct 2026 copy) (10-12N) para a(3) (mobility and countermobility missions)
- 12N: What is the most important safety rule around heavy equipment?
- Only tested and licensed operators inspect and run the equipment; keep guards and safety devices in place; post a warning device or a signal person (in a reflective orange vest when possible) where moving equipment endangers workers; and use spotters for dumping and when the bucket is out of the operator's sight.
- TM 3-34.62 (30 May 2025 incl C1) ch. 13 (Safety Program) paras 13-4, 13-5, 13-7 and 13-8; paras 7-35 (bucket spotter or signalman) and 10-7 ("Always use spotters to oversee dumping operations")
- 12N: What is "cut and fill"?
- Removing soil from high areas (cut) and placing it in low areas (fill) to achieve the required grade.
- ATP 3-34.40 (14 Apr 2023) para 7-91 (cut and fill brings the route elevation to grade; biggest part of road earthwork)
- 12N: What is the skill progression for 12N?
- 12N1O equipment operator; 12N2O Horizontal Construction Sergeant; 12N3O Horizontal Construction Supervisor/Section Sergeant; 12N4O Senior Horizontal Construction Supervisor/Platoon Sergeant; at SL5, 12X General Engineering Supervisor (E8).
- DA Pam 611-21 ch. 10C (Oct 2026 copy) (10-12N) para a(1)-(4); DA Pam 611-21 ch. 10 MOS/skill-level classification listing (chapter-10-base) (12N1-4; 12X5 General Engineering Supervisor, E8); DA Pam 611-21 ch. 10C (Oct 2026 copy) (10-12X) para a
- 12N: How does DA Pam 611-21 summarize the 12N major duties?
- The horizontal construction engineer supervises or serves as a member of a squad, team, section, or platoon. (ch. 10C)
- DA Pam 611-21 ch. 10C (Oct 2026 copy) (10-12N) para a
- 12N: What minimum ASVAB line score does DA Pam 611-21 list for 12N?
- 85 in GM (General Maintenance) (ch. 10C; verify current standards).
- DA Pam 611-21 ch. 10C (Oct 2026 copy) (10-12N) para b(4)(a) (GM 85, effective 9 Oct 2023; checked against 10C)
- 12N: What physical demands rating applies to 12N?
- Moderate (Gold), with a minimum physical profile of 222221 (ch. 10C).
- DA Pam 611-21 ch. 10C (Oct 2026 copy) (10-12N) paras b(1)-(2) (10C also requires b(3) red/green color discrimination)
- 12N: Under whose auspices is the 12N MOS course conducted?
- The USA Engineer Center and School (DA Pam 611-21 ch. 10C).
- DA Pam 611-21 ch. 10C (Oct 2026 copy) (10-12N) para b(6)
- 12N: What does DA Pam 611-21 list as 12N duties at skill level 2?
- Serves as a Horizontal Construction Sergeant with limited supervision of construction equipment and personnel activities. (ch. 10C)
- DA Pam 611-21 ch. 10C (Oct 2026 copy) (10-12N) para a(2) (MOSC 12N2O)